Bangalore/Project record

K-RERA · the public record

AKSHAYA REGALIA

Bengaluru South · AKSHAYA BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2018declared completionK-RERA registration · read 20 Sep 2026
0registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.9registered acres

0.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/180420/001539

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 March 2018
Land area7,659 sq m (1.9 acres)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered land area7,659 sqmThe land area attached to this K-RERA registration.
Parking total (reconciled)170Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field170Separate filed counts; these categories may overlap and are not added together.
Project start date14-05-2014

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 36 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Mar 2018 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (8 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
BALAPPA RAMAPPA MALED vs AKSHAYA BUILDERS AND DEVELOPERSSupport from RERA to fix the said problems in complaint copy and recover the out of pocket expenses for correcting the flat problems.AUTHORITY27/12/2022
Yashwanth Kumar B S vs AKSHAYA BUILDERS AND DEVELOPERSDirect the respondent to strictly follow provisions of RERA Act 2016 and compensate for the financial lossAUTHORITY05/07/2025
MUKUNDA J N vs AKSHAYA BUILDERS AND DEVELOPERSRequest the Honourable Authority to pass an order directing the respondent to rectify the above mentioned defectsAUTHORITY01/08/2025
Anantha Shankar T R vs AKSHAYA BUILDERS AND DEVELOPERSi. Direct the respondent to strictly follow provisions of RERA Act 2016 by forming a legal body & complete the title conveyance to the juristic person to maintain common areas & assets of the propertyAUTHORITY01/08/2025
Shubha Bhat vs AKSHAYA BUILDERS AND DEVELOPERSAs per the facts of complaint mentionedAUTHORITY01/08/2025
Srinivas Venkatesh Mokshagundam vs AKSHAYA BUILDERS AND DEVELOPERSRequest RERA to instruct Builder to maintain the apartment complex and to share the Appropriate bills with the flat ownersAUTHORITY01/08/2025
Sandhiya A vs AKSHAYA BUILDERS AND DEVELOPERSDirect the respondent to strictly follow provisions of RERA Act 2016 & provide relief per section 18AUTHORITY01/08/2025
Umesh P vs AKSHAYA BUILDERS AND DEVELOPERSAs per the details furnished in facts of complaintAUTHORITY01/08/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (8 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/201019/0006913
19-10-2020
Pending amenities and Statutory Approvals and Individual flat issuesAKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201019/0006909
19-10-2020
COMPLANT UNDER SECTION 31 OF THE REAL ESTATE REGULATION AND DEVELOPMENT ACT, 2016AKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201019/0006863
19-10-2020
Non completion of duties as per section 11 of The Real Estate (Regulation and Development)Act, 2016AKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201021/0006930
21-10-2020
Builder has failed to maintain the Apartment complexAKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201026/0006960
26-10-2020
MEMORANDUM OF COMPLANT UNDER SECTION 31 OF THE REAL ESTATE REGULATION AND DEVELOPMENT ACT, 2016AKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201027/0006964
27-10-2020
COMPLANT UNDER SECTION 31 OF THE REAL ESTATE REGULATION AND DEVELOPMENT ACT, 2016AKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201107/0007030
07-11-2020
Builder absconded without completing the terms of agreement, handoverAKSHAYA REGALIADISPOSED AUTHORITY FULLBENCH
CMP/201125/0007059
25-11-2020
Association Not Formed, broken floor tiles not replaced, bathroom wall water leakage, wall dampening, poor water quality, etcAKSHAYA REGALIADISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Builder track record

RERA filing

Akshaya Builders has 2 other K-RERA-registered projects in our records. 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Union Bank of India JAYANAGAR (IFSC UBIN0537942, a/c …6510). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 2 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre12 km
Electronic City16 km
Bellandur–Marathahalli belt18 km
Outer Ring Road / Manyata19 km
Whitefield IT hub26 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Akshaya Builders.
Akshaya Builders has 3 projects registered in Bangalore.
1 complaints on the K-RERA register against Akshaya Builders in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Rajarajeshwari Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Akshaya Regalia?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026