Bangalore/Project record

K-RERA · the public record

ARS Signaturehomes Phase-2

Anekal · ARS INFRAA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2025declared completionK-RERA registration · read 20 Sep 2026
253registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

BLOCK-1
101
BLOCK-2
152

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.6registered acres

70.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/300124/006588

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 July 2025
Land area14,619 sq m (3.6 acres)
Homes registered253
Tower/wing entries2
Unit mix101 × BLOCK-1, 152 × BLOCK-2

In context

Density70 homes per acre
Density in context41st percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units253Total inventory registered with K-RERA.
Official carpet area732 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area44,680 sqmUseful scale context when comparing density and project cost.
Registered land area14,619 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)282Separate filed counts; these categories may overlap and are not added together.
Covered-parking field252Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number371Use this to match the sanctioned drawing set shown by the builder.
Plan approval date21-11-2023
Project start date27-11-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
BLOCK-110140%12,569 sqm
BLOCK-215260%18,562 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BLOCK-1810110127 m
BLOCK-2815218127 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 253 official flat/unit rows, matching the 253 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK20679.9-125.0 sqm42.5-63.5 sqm206
2 BHK4659.4-75.9 sqm38.9-39.2 sqm46
4 BHK1343.5 sqm196.1 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BLOCK-215281.8-123.9 sqm42.5-62.9 sqm152
BLOCK-110159.4-343.5 sqm38.9-196.1 sqm101
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101BLOCK-113 BHK125.0 sqm63.5 sqm1
102BLOCK-112 BHK75.9 sqm39.2 sqm1
103BLOCK-112 BHK75.4 sqm38.9 sqm1
104BLOCK-113 BHK91.0 sqm46.9 sqm1
105BLOCK-113 BHK91.0 sqm46.9 sqm1
106BLOCK-112 BHK75.9 sqm39.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 43 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Jul 2025 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantVINUTH H S2255042011Bengaluru Urban, Karnataka - 560060
EngineerRAMESHA D BBCC/BL-3.6E-3959/2014-152011Bengaluru Urban, Karnataka - 560076
ArchitectRAMESHA D BBCC/BL-3.6E-3959/2014-152011Bengaluru Urban, Karnataka - 560076
Contractor1213-2011Bengaluru Urban, Karnataka - 560001

Builder track record

RERA filing

Ars Infraa has 3 other K-RERA-registered projects in our records (average reported construction progress 64%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹49.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank RENUKA NAGAR SARJAPURA BRANCH IFSC Code : ICIC0001075 Pin Code : 562125. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub11 km
Bellandur–Marathahalli belt11 km
Electronic City12 km
MG Road / city centre21 km
Outer Ring Road / Manyata25 km
Kempegowda Int'l Airport37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ars Infraa.
Ars Infraa has 4 projects registered in Bangalore.

Other projects by this builder in Bangalore

ARS Zurich Phase-1
On track · 80% built · 32% sold
ARS Zurich Phase-2
Due soon · 47% built · 50% sold

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.