Bangalore/Project record

K-RERA · the public record

BELAKU

Bengaluru South · Millennial Luxury Estates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

21%construction reportedQ4 2025 filing
19units not bookedof 23 · Q4 2025 filing
31 Mar 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

31 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4BHK
19
3BHK
4

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.7registered acres

31.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/180924/007041

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2026
Land area2,934 sq m (0.7 acres)
Homes registered23
Tower/wing entries1
Unit mix19 × 4BHK, 4 × 3BHK

In context

Density31.7 homes per acre
Density in context9th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units23Total inventory registered with K-RERA.
Official carpet area5,474 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area11,663 sqmUseful scale context when comparing density and project cost.
Registered land area2,934 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)54Separate filed counts; these categories may overlap and are not added together.
Covered-parking field54Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-04-2024
Project start date01-03-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4BHK1983%4,627 sqm
3BHK417%849 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Belaku11235439.55 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 23 official flat/unit rows, matching the 23 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK19225.1-255.1 sqm120.8-136.0 sqm38
3 BHK4199.0-222.2 sqm108.1-119.0 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Belaku23199.0-255.1 sqm108.1-136.0 sqm46
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G-BBelaku04 BHK225.1 sqm121.6 sqm2
1-ABelaku13 BHK199.0 sqm108.1 sqm2
1-BBelaku14 BHK225.1 sqm120.8 sqm2
2-ABelaku24 BHK233.3 sqm125.5 sqm2
2-BBelaku24 BHK255.1 sqm134.7 sqm2
3-ABelaku34 BHK232.2 sqm124.9 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

5 of 35 compliance document slots are filed as Not Applicable; the remaining 30 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved10-10-2023BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved10-10-2022KSPCB - signed.pdf
KPTCL- BESCOMApproved05-09-2023BESCOM NOC.pdf
Fire and SafetyApproved21-07-2023Fire.pdf
Airport Authority of IndiaApproved30-08-2023HAL.pdf
BSNL/Telecommunication DepartmentApproved02-09-2024BSNL NOC.PDF

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSiddharrth Mehta2070432020Chennai, Tamil Nadu - 600113
EngineerRAVURI PHANIDHAR VARAPRASADBCCL/BL-3.6/SE-0313/23-242010Bengaluru Urban, Karnataka - 560094
ArchitectVEDA T NCA/2017/853012017Bengaluru Urban, Karnataka - 560072
ContractorBCD LLP-1952Bengaluru Urban, Karnataka - 560008

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹7.31 Cr collected from buyers, ₹6.49 Cr withdrawn from the project's escrow account.

Construction progress20% → 21% (+1 pts)
Units sold/booked as registered4/23 (17%)
Buyer collections in available QPRs₹13.61 Cr
Escrow withdrawals in available QPRs₹12.32 Cr (0.91x collections)
  • Construction progress moved from 20% to 21% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹215.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC BANGALORE - KASTURBA GANDHI MARG IFSC Code : HDFC0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre6 km
Bellandur–Marathahalli belt6 km
Electronic City10 km
Outer Ring Road / Manyata13 km
Whitefield IT hub14 km
Kempegowda Int'l Airport31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Millennial Luxury.

Other RERA-registered projects in Nagarbhavi

Construction Of 3bhk Housing Project In Sy No 103 Of Nagarbhavi Yeshwanthapura Hobli Bangalore

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Belaku?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026