Evershine NORTHEAST Apartments

Anekal · Evershine Dwellings

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
57units not bookedof 168 · Q1 2026 filing
30 Sep 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Sep 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
12

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.7registered acres

98.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/220210/004690

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 September 2026
Land area6,930 sq m (1.7 acres)
Homes registered168
Tower/wing entries2
Unit mix12 × 2 BHK

In context

Density98.1 homes per acre
Density in context78th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units168Total inventory registered with K-RERA.
Official carpet area595 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area6,930 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.24Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)168Separate filed counts; these categories may overlap and are not added together.
Open-parking field17Separate filed counts; these categories may overlap and are not added together.
Garage field168Separate filed counts; these categories may overlap and are not added together.
Project start date01-10-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK12100%595 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block A68484-
Block B68484-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 168 official flat/unit rows, matching the 168 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK13249.6-57.2 sqm33.5-38.9 sqm132
3 BHK3673.6 sqm51.6 sqm36

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block A8449.6-73.6 sqm33.5-51.6 sqm84
Block B8449.6-73.6 sqm33.5-51.6 sqm84
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-101Block A12 BHK57.2 sqm38.9 sqm1
A-102Block A12 BHK57.2 sqm38.9 sqm1
A-103Block A12 BHK57.2 sqm38.9 sqm1
A-104Block A12 BHK57.2 sqm38.9 sqm1
A-105Block A12 BHK57.2 sqm38.9 sqm1
A-106Block A12 BHK57.2 sqm38.9 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 21 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
KSPCB- PCB (10 Acres to 125 Acres)Approved27-04-2020PCB NOC.pdf
KPTCL- BESCOMApproved18-06-2020BESCOM NOC.pdf
Fire and SafetyApproved19-05-2020FIRE NOC.pdf
Labour and Education DepartmentApproved13-04-2022Labour License.pdf
Airport Authority of IndiaApproved13-10-2020AIRPORT NOC.pdf
BSNL/Telecommunication DepartmentApproved04-01-2021BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRamesh .D.B-2012JP Nagar 2nd Phase, Bangalore
ContractorDoggala Thimmareddy-2015Haddosiddhapura, Sarjapura Road
Structural engineerG.Praveen Kumar---

Builder track record

RERA filing

Evershine Dwellings has 2 other K-RERA-registered projects in our records (average reported construction progress 8%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.03 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹0.03 Cr) exceeded buyer collections (₹0.00 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress99% → 100% (+1 pts)
Units sold/booked as registered111/168 (66%)
Buyer collections in available QPRs₹0.64 Cr
Escrow withdrawals in available QPRs₹0.65 Cr (1.02x collections)
  • Construction progress moved from 99% to 100% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 1.02x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹21.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Industrial Development Bank of India Koramangala 5th Block (IFSC IBKL0000693, a/c …6861). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City4 km
Bellandur–Marathahalli belt7 km
Whitefield IT hub13 km
MG Road / city centre15 km
Outer Ring Road / Manyata21 km
Kempegowda Int'l Airport37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Evershine Dwellings.
Evershine Dwellings has 3 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Evershine Stonepark
On track · 8% built · 3% sold

Other RERA-registered projects in Gattahalli

Major developers building in Gattahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.