RERA Property Intelligence Report · Preview

PINNACLE

GLOBAL GREENS BUILDERS AND DEVELOPERS S S PRASAD AND N BRAHMANANDA · Bengaluru South · K-RERA PRM/KA/RERA/1251/310/PR/190823/002812

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

Registered units
₹17.0 Cr
Est. construction cost
Units profiled
23
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered land area2,478 sqmThe land area attached to this K-RERA registration.
Parking disclosed52 total (0 open)Confirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-04-2018

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 17 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Dec 2020, extended (Covid Extension) to 30 Sep 2021 — both dates have passed with no OC on file. An extension application filed on 21 Jul 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (16 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Amitava Mukhopadhyay vs Landstar HomesDirect the Respondents to refund all payments made by the Complainant, including EMIs, and repay the outstanding home loan associated with Account No.637109559, obtaining an NOC from HDFC.AUTHORITY28/07/2025
ANSHU KUMAR SINHA vs PinncleEntire refund along with interest and direction to the bank to close the loan amountAUTHORITY21/01/2026
Praveen Kumar Sinha vs Landstar HomesRefund of Rs 13 lakhs and Rs 42,11,600 of bank loan of IDBI with all penalty interest charges and compensation of 1 croreAUTHORITY17/12/2025
Manju Manikya vs Landstar HomesCancel the booking of Unit in Question and refund earnest amount of Rs. 24,15,000 to complainant and loan amount of Rs. 35,22,000 directly to SBI along with future interest and penalties, if any.AUTHORITY17/12/2025
Mallikarjuna Reddy N vs Landstar HomesWe urge the builder to deliver the flats without any further delay and to provide delay period interest for such periodAUTHORITY15/06/2026
Harshit Mohan vs Landstar HomesDeveloper be directed to refund the earnest money paid by complainant and close the loan accountAUTHORITY05/04/2025
HARSHIT MOHAN vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY05/04/2025
Harshit Mohan vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY05/04/2025
Praveen Kumar Sinha vs Landstar HomesRefund of Rs 13 lakhs and Rs 42,57,332 of bank loan of SBI with all penalty interest charges and compensation of 1 croreAUTHORITY05/04/2025
Ramesh Babu Maguluri vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY03/04/2025
Kuldeep Singh vs Landstar HomesOrder the respondents to refund entire amount along with interest paid by the complainant and directions to Respondents to repay the entire outstanding of LoanAUTHORITY02/04/2025
Mallikarjuna Reddy N vs Landstar HomesWe urge the builder to deliver the flats without any further delay and to provide delay period interest for such periodAUTHORITY02/02/2026
UPENDRA PRASAD vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY01/04/2025
UPENDRA PRASAD vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY01/04/2025
KIRAN PADAMANNOOR vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY01/04/2025
KIRAN PADAMANNOOR vs Landstar HomesDeveloper be directed to refund the complainant and close the loan accountAUTHORITY01/04/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: ORIENTAL BANK OF COMMERCE HRBR LAYOUT (IFSC ORBC0101562, a/c …0655). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre5 km
Bellandur–Marathahalli belt12 km
Outer Ring Road / Manyata12 km
Electronic City14 km
Whitefield IT hub19 km
Kempegowda Int'l Airport32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Global Greens.

Other RERA-registered projects in Basavanagudi

Major developers building in Basavanagudi

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Pinnacle?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026