Bangalore/Project record

K-RERA · the public record

RNS Shrinikethan

Bengaluru North · RNS Infrastructure

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2020declared completionK-RERA registration · read 20 Sep 2026
252registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3BHK FLATS-180,4BHK FLATS-72
240

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.9registered acres

51.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/171031/001215

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2020
Land area19,899 sq m (4.9 acres)
Homes registered252
Tower/wing entries7
Unit mix240 × 3BHK FLATS-180,4BHK FLATS-72

In context

Density51.2 homes per acre
Density in context25th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units252Total inventory registered with K-RERA.
Official carpet area52,290 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area19,899 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.733Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries7Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)504Separate filed counts; these categories may overlap and are not added together.
Open-parking field120Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date24-01-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3BHK FLATS-180,4BHK FLATS-72240100%52,290 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A Gulabi173672-
B Kamala173672-
C-Kanakambara173672-
D-Mallige173672-
E-Parijata173672-
F-Sevanthige173672-
G-Sampige173672-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 252 official flat/unit rows, matching the 252 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
Not stated120196.2-220.7 sqm67.8-74.4 sqm240
4BHK72203.2-237.6 sqm69.1-80.2 sqm144
3BHK36189.1-220.3 sqm64.6-74.2 sqm72
3 BHK + Study24210.1-218.5 sqm71.2-73.9 sqm48

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A Gulabi36203.3-237.6 sqm69.1-80.0 sqm72
B Kamala36203.2-237.6 sqm69.2-80.2 sqm72
C-Kanakambara36198.8-218.5 sqm67.8-73.9 sqm72
D-Mallige36189.1-220.3 sqm64.6-74.1 sqm72
E-Parijata36199.1-219.8 sqm67.9-74.2 sqm72
F-Sevanthige36199.2-219.7 sqm67.8-74.0 sqm72
G-Sampige36196.2-220.7 sqm68.0-74.4 sqm72
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A 001A Gulabi04BHK203.3 sqm69.1 sqm2
A 002A Gulabi04BHK203.8 sqm69.8 sqm2
A 101A Gulabi14BHK203.3 sqm69.1 sqm2
A 102A Gulabi14BHK203.8 sqm69.8 sqm2
A 201A Gulabi24BHK237.6 sqm80.0 sqm2
A 202A Gulabi24BHK228.3 sqm77.4 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

8 of 36 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2020, extended (Covid Extension) to 30 Mar 2021 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
DEEPAK DEVRAJ vs RNS SHRINIKETHANHALT CONSTRUCTION AND MARKETING OF PROJECTAUTHORITY01/07/2019

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹143.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Yeshwantpur (IFSC SBIN0003297, a/c …9613). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre8 km
Outer Ring Road / Manyata9 km
Bellandur–Marathahalli belt18 km
Electronic City22 km
Whitefield IT hub23 km
Kempegowda Int'l Airport28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Rns Infrastructure.

Other RERA-registered projects in Basaveshwar Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.