What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
Litigation on file
Legal status
34
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

Registered units
₹9.0 Cr
Est. construction cost
Units profiled
25
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered land area48,916 sqmThe land area attached to this K-RERA registration.
Project start date10-04-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential Plots187100%0 sqm

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

2 of 19 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

3 of 5 applicable approvals are on file; still outstanding: Water supply and sewage board and KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApplied20-06-2019View NOC
KSPCB- PCB (10 Acres to 125 Acres)Approved21-03-2022KSPCB NOC.pdf
Engineering Department (PWD) for completion of development worksApproved10-09-2020PWD NOC.pdf
KPTCL- BESCOMTo Be Applied-View NOC
Horticulture departmentApproved22-12-2020HORTICULTURE NOC.pdf

Builder track record

RERA filing

Saha Developers has 34 other K-RERA-registered projects in our records (average reported construction progress 97%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress98% → 99% (+1 pts)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre8 km
Electronic City14 km
Bellandur–Marathahalli belt14 km
Outer Ring Road / Manyata15 km
Whitefield IT hub22 km
Kempegowda Int'l Airport35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Saha Developers. View Saha Developers's full track record →
Saha Developers has 35 projects registered in Bangalore, 9 completed.

Other projects by this builder in Bangalore

Currency Layout 1
Filing overdue · 97% built
Saha Elegance 2
Filing overdue · 98% built
Saha Meadows
Filing overdue · 99% built
Saha Splendid
Filing overdue · 100% built
Skanda Enclave 1
Filing overdue · 99% built
Skanda Enclave 2
Filing overdue · 99% built

Other RERA-registered projects in Banashankari

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Skanda Enclave 3?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026