Bangalore/Project record

K-RERA · the public record

Sobha Royal Crest

Bengaluru South · SOBHA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

60%construction reportedQ1 2026 filing
0units not bookedof 329 · Q1 2026 filing
31 Dec 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK
6
Total Flats (3 BHK and 4 BHK)
329
3 BHK
323

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

6.3registered acres

52.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/300522/004936

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2028
Land area25,619 sq m (6.3 acres)
Homes registered329
Tower/wing entries3
Unit mix6 × 4 BHK, 329 × Total Flats (3 BHK and 4 BHK), 323 × 3 BHK

In context

Density52 homes per acre
Density in context19th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units329Total inventory registered with K-RERA.
Official carpet area40,799 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area86,676 sqmUseful scale context when comparing density and project cost.
Registered land area25,619 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.18Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)329Separate filed counts; these categories may overlap and are not added together.
Covered-parking field459Separate filed counts; these categories may overlap and are not added together.
Open-parking field36Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDSOUTH/0010/21-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date12-05-2022
Project start date14-06-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK61%1,142 sqm
Total Flats (3 BHK and 4 BHK)32950%40,799 sqm
3 BHK32349%39,657 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing 131110110100 m
Wing 231109109100 m
Wing 331110110100 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 329 official flat/unit rows, matching the 329 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK323115.4-126.5 sqm53.3-62.9 sqm323
4 BHK6182.2-206.4 sqm90.1-100.2 sqm6

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing 1110115.4-182.2 sqm53.3-91.1 sqm110
Wing 3110115.4-182.2 sqm53.3-91.1 sqm110
Wing 2109126.1-206.4 sqm57.8-100.2 sqm109
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1041Wing 143 BHK126.5 sqm62.9 sqm1
1042Wing 143 BHK115.4 sqm56.9 sqm1
1043Wing 143 BHK115.4 sqm56.9 sqm1
1044Wing 143 BHK126.5 sqm62.9 sqm1
1051Wing 153 BHK126.5 sqm57.4 sqm1
1052Wing 153 BHK115.4 sqm53.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • OS No 4654/2004 filed by Smt A C Sharadamma and others against Sri AC Ananthaswamy and Others for partition of suit schedule properties. Compromise reported to the Court and Interim Order was vacated vide Order dated 23.06.2023 — City Civil Court CCH2 Bengaluru (2004)

12 of 83 compliance document slots are filed as Not Applicable; the remaining 71 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Mrudula Vijayendra vs SOBHA LIMITED1. Rs. 30,000/= to be paid back to me by Sobha. 2. They delayed the payment big time and I demand interest charges for the delayAUTHORITY17/11/2023
Muddu Prasad V vs SOBHA LIMITEDSobha LTD is not adhereing to the contract and are deducting more than 1% of apartment cost as banking charges and not sharing any proof w.r.t those charges. Need your intervention for complete refundAUTHORITY16/03/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (127 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190217/0002175
17-02-2019
Compensation for Delay of projectsSobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190218/0002166
18-02-2019
Refund of booking amountSobha Dream Acres - Palm Springs Phase 17 Wing 54 (another project by this promoter)DISPOSED AO
CMP/190225/0002263
25-02-2019
Refund of Advance amount-Sobha Arena - The Park ( Block 2 ) (another project by this promoter)DISPOSED AO
CMP/190308/0002388
08-03-2019
Non-allotment of agreed units & RefundSobha Indraprastha (another project by this promoter)DISPOSED AO
CMP/190308/0002322
08-03-2019
Promoter SL Demanding 38% payment of unit cost before entering the ATSSobha Arena - Pebble Court (Block 1) (another project by this promoter)DISPOSED AO
CMP/190315/0002219
15-03-2019
About refund of booking amountSobha Dream Acres - Tropical Greens Phase 8 Wing 43 and 44 (another project by this promoter)DISPOSED AO
CMP/190324/0002505
24-03-2019
Compensation against late deliverySobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190401/0002556
01-04-2019
Please refund booking amountSobha Dream Acres - Rain Forest Phase 2 Wing 3 and 4 (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved03-03-2022BWSSB NOC SRC 03032022.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved20-11-2021KSPCB CFE SRC 20112021.pdf
KPTCL- BESCOMApproved06-08-2025BESCOM NOC SRC 06082025.pdf
Fire and SafetyApproved18-10-2021Fire NOC SRC 18102021 Compresed.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBalaji D2173902016Bengaluru Urban, Karnataka - 560084
EngineerMr. Durga Prasad KVRSE-192/2015-162020Bengaluru Urban, Karnataka - 560103
ArchitectVinita AgastCA/95/191971995Bengaluru Urban, Karnataka - 560103
ContractorSobha Limited-1995Bengaluru Urban, Karnataka - 560103

Builder track record

RERA filing

Sobha has 121 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sobha”) (average reported construction progress 61%). 60 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹14.28 Cr collected from buyers, ₹13.48 Cr withdrawn from the project's escrow account.

Construction progress60% → 60% (+0 pts)
Units sold/booked as registered329/329 (100%)
Buyer collections in available QPRs₹44.30 Cr
Escrow withdrawals in available QPRs₹78.69 Cr (1.78x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • Across available QPR rows, escrow withdrawals are 1.78x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹85.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank M G ROAD IFSC Code : UTIB0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre10 km
Electronic City16 km
Outer Ring Road / Manyata16 km
Bellandur–Marathahalli belt17 km
Whitefield IT hub24 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sobha. View Sobha's full track record →
Sobha has 120 projects registered in Bangalore, 25 completed.
274 complaints on the K-RERA register against Sobha in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.6/5

337 reviews for Sobha in Bangalore
Read 337 reviews on MouthShut →

Other projects by this builder in Bangalore

Sobha Crystal Meadows Phase 1 Wing 1 To 6
Filing overdue · 5% built · 0% sold
Sobha Crystal Meadows Phase 2 Wing 7 And 8
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 3 Wing 9 To 15
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 4 Wing 23 To 28
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 5 Wing 16 To 22
Filing overdue · 2% built · 0% sold
Sobha Dream Acres - Tropical Greens Phase 21 Wing 21 And 22
Filing overdue · 100% built · 100% sold

Other RERA-registered projects in Banashankari

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sobha Royal Crest?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026