RERA Property Intelligence Report · Preview

Solus 2 Phase I

Mythri Housing · Bengaluru South · K-RERA PRM/KA/RERA/1251/310/PR/171015/000729

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

58
Registered units
₹29.5 Cr
Est. construction cost
Units profiled
41
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units58Total inventory registered with K-RERA.
Official carpet area140 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area2,906 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.39Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed153 total (0 open) — 2.64 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-10-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Ground floor Office B1100%140 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Not Applicable558153-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 58 official flat/unit rows, matching the 58 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
COMMERCIAL58605.8-4,627.4 sqft185.2-1,415.8 sqft58

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Not Applicable58605.8-4,627.4 sqft185.2-1,415.8 sqft58
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A 0Not Applicable0COMMERCIAL2,905.8 sqft895.7 sqft1
B 0Not Applicable0COMMERCIAL1,506.3 sqft457.7 sqft1
C 0Not Applicable0COMMERCIAL4,627.4 sqft1,415.8 sqft1
A 01Not Applicable1COMMERCIAL992.1 sqft312.5 sqft1
B 01Not Applicable1COMMERCIAL838.8 sqft254.9 sqft1
C 01Not Applicable1COMMERCIAL777.3 sqft242.6 sqft1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~908 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a boutique, low-density project — 58 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 153 parking spaces for 58 homes (~2.6 per home) — comfortable headroom over the 1-per-home many projects offer.
Your land share (UDS)Undivided land share averages ~316 sqft per home; across all 58 homes that is ~59% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 36 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Aug 2019, extended (Section 6 Extension) to 31 Aug 2020 — both dates have passed with no OC on file. The extension on file was granted on 20 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/220620/000729) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (7 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
NITHIN MAHADEVAPPA vs SOLUS 2 PHASE 1(a) Interest for every month of delay, till the handing over of the possession to the Complainants by the respondents (b) to execute an agreement of sale in favour of Complainants by the Respondents.AUTHORITY30/07/2025
Sivasankaran M S vs M/s. Mythri Housing Pvt.Ltd., & M/s Gururaj Enterprises Pvt.LtdRefund of Rs 69,57,347 + Interest of Rs 39,03,808 + Compensation of Rs 1,00,00,000 + Future interest of Rs 2097 per day till date of paymentAUTHORITY19/11/2024
DR B K PRABHAKARA RAO vs Solus 2 phase 1Interest for every month of delay, till the handing over of the possession to the complainants and to impose penalty to the respondents for violation of RERA Act and Rules.AUTHORITY11/08/2025
MR SACHINKUMAR BP vs MYTHRI HOUSING PVT LTDInterest for every month of delay, till the handing over of the possession to the complainants and impose penalty to the respondents for violation of RERA Act and Rules.AUTHORITY11/08/2025
MR SACHINKUMAR BP vs MYTHRI HOUSING PVT LTDInterest for every month of delay, till the handing over of the possession to the complainants and impose penalty to the respondents for violation of RERA Act and Rules.AUTHORITY11/08/2025
MRS G MAHESWARI vs Solus 2 phase 1Interest for every month of dealy, till the handing over of the possession to the complainant by the respondents and to impose penalty to the respondents for violation of RERA Act and Rules.AUTHORITY11/08/2025
VASANTHI MURUGESH vs Mythri Housing Private LimitedInterest for every month of delay, till the handing over of the possession and impose penalty to the respondents for violation of RERA Act and RulesAUTHORITY02/12/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (2 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/220919/0010023
19-09-2022
Complaint U/Sec.31 of RERA Act, 2016 against the respondents who fails to complete or is unable to give possession of Commercial Unit No.C-5 to the Complainant within 24 months from date of AgreementSolus 2 Phase IDISPOSED AUTHORITY BENCH4
CMP/211218/0008733
18-12-2021
Complaint U/Sec.31 of RERA Act,2016 for violation of terms of Agreement for Sale and Addendum Agreement & Sec.3 & 6, 6th Floor is constructed without sanctioned plan & Rera approval.Solus 2 Phase IPOSTED FOR ORDERS AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectKhan Global Engineering consultants Pvt Ltd for facade-2003Indiranagar, Bangalore
ContractorPERFECT CONSTRUCTIONS-2013Marathahalli, Bangalore
Structural engineerShradha Designtech Pvt Ltd---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹50.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kasturba Road (IFSC HDFC0000009, a/c …8291). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload from Jul 2017.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata10 km
Bellandur–Marathahalli belt11 km
Electronic City15 km
Whitefield IT hub18 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mythri Housing.

Other RERA-registered projects in Kalasipalya

Construction OF 1292 GF, 108 G+1 AT Raichur City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Solus 2 Phase I?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026