34%construction reportedQ1 2026 filing
50units not bookedof 725 · Q1 2026 filing
15 Jan 2032declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

15 Jan 2032

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Residential
725

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

6.1registered acres

118.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/290125/007454

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion15 January 2032
Land area24,796 sq m (6.1 acres)
Homes registered725
Tower/wing entries1
Unit mix725 × Residential

In context

Density118.3 homes per acre
Density in context88th percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units725Total inventory registered with K-RERA.
Official carpet area44,324 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area87,330 sqmUseful scale context when comparing density and project cost.
Registered land area24,796 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)45Separate filed counts; these categories may overlap and are not added together.
Covered-parking field622Separate filed counts; these categories may overlap and are not added together.
Open-parking field138Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/188/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date24-12-2024
Project start date16-01-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential725100%44,324 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Building1672545760 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 725 official flat/unit rows, matching the 725 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK34865.2-85.8 sqm31.4-42.1 sqm348
2 BHK30749.9-55.5 sqm24.7-30.4 sqm307
1 BHK7028.7-29.1 sqm14.3-14.5 sqm0 (70 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Building72528.7-85.8 sqm14.3-42.1 sqm655 (70 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101Building12 BHK49.9 sqm24.8 sqm1
102Building13 BHK85.8 sqm42.1 sqm1
103Building13 BHK81.1 sqm41.6 sqm1
104Building12 BHK55.5 sqm28.3 sqm1
105Building12 BHK55.5 sqm28.3 sqm1
106Building13 BHK81.1 sqm41.6 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

7 of 34 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/221107/0010223
07-11-2022
Not returning back my token amount as promisedSOWPARNIKA INDRADHANUSH PHASE I (another project by this promoter)DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved21-02-2024Sowparnika Rhythm of Rain NOC Panchayat Water .pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved16-11-2024Sowparnika Rhythm of Rain NOC KSPCB.pdf
KPTCL- BESCOMApproved01-06-2024Sowparnika Rhythm of Rain NOC BESCOM.pdf
Fire and SafetyApproved06-12-2024Sowparnika Rhythm of Rain NOC Fire.pdf
Airport Authority of IndiaApproved17-04-2024Sowparnika Rhythm of Rain NOC AAI.pdf
BSNL/Telecommunication DepartmentApproved03-01-2024Sowparnika Rhythm of Rain NOC BSNL.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantCHITTEPU YESHWANT REDDY2510692018Bengaluru Urban, Karnataka - 560102
EngineerVAIBHAV KUMAR J GBCC/BL-3.6 SE-0016/23-242013Bengaluru Urban, Karnataka - 560037
ArchitectMANIRAJ DCA/2011/516952004Bengaluru Urban, Karnataka - 560037
ContractorSOWPARNIKA HOMES PRIVATE LIMITED-2014Bengaluru Urban, Karnataka - 560037

Builder track record

RERA filing

Sowparnika Homes has 3 other K-RERA-registered projects in our records (average reported construction progress 82%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹34.16 Cr collected from buyers, ₹34.16 Cr withdrawn from the project's escrow account.

Construction progress9% → 34% (+25 pts)
Units sold/booked as registered675/725 (93%)
Buyer collections in available QPRs₹215.99 Cr
Escrow withdrawals in available QPRs₹215.99 Cr (1.00x collections)
  • Construction progress moved from 9% to 34% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹36.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC OLD AIRPORT ROAD IFSC Code : HDFC0000075 Pin Code : 560017. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt13 km
Outer Ring Road / Manyata20 km
MG Road / city centre20 km
Electronic City21 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sowparnika Homes.
Sowparnika Homes has 4 projects registered in Bangalore, 2 completed.
2 complaints on the K-RERA register against Sowparnika Homes in Bangalore.

Other projects by this builder in Bangalore

Sowparnika Euphoria IN THE East
On track · 50% built · 98% sold
Sowparnika Indradhanush Phase I
On track · 98% built · 99% sold
Sowparnika Indradhanush Phase II
On track · 98% built · 99% sold

Other RERA-registered projects in Whitefield

Major developers building in Whitefield

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sowparnika Rhythm Of Rain?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026