Bangalore/Project record

K-RERA · the public record

SURYA VALENCIA Phase I

Yelahanka · SURYA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

48%construction reportedQ1 2026 filing
16units not bookedof 44 · Q1 2026 filing
31 Dec 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK and 5 BHK
44

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.6registered acres

12.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/472/PR/171224/007305

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2028
Land area14,770 sq m (3.6 acres)
Homes registered44
Tower/wing entries5
Unit mix44 × 4 BHK and 5 BHK

In context

Density12.1 homes per acre
Density in context3rd percentile of 125 Yelahanka projects (median 76)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units44Total inventory registered with K-RERA.
Official carpet area10,906 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area12,978 sqmUseful scale context when comparing density and project cost.
Registered land area14,770 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)88Separate filed counts; these categories may overlap and are not added together.
Covered-parking field88Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberDPA/TP/CC/197/24-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date08-11-2024
Project start date08-11-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK and 5 BHK44100%0 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 144814 m
Block 2 Part A44814 m
Block 2 Part B351010.75 m
Block 3371410.75 m
Block 44244814 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 44 official flat/unit rows, matching the 44 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
5 BHK32256.5-262.1 sqm302.0-309.5 sqm64
4 BHK12205.6-223.3 sqm242.7-264.9 sqm24

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 424260.0 sqm303.9-307.5 sqm48
Block 37223.3 sqm262.2-264.9 sqm14
Block 2 Part B5205.6 sqm242.7-245.7 sqm10
Block 14258.0 sqm302.0-305.4 sqm8
Block 2 Part A4256.5-262.1 sqm303.9-309.5 sqm8
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1Block 115 BHK258.0 sqm303.8 sqm2
2Block 125 BHK258.0 sqm302.0 sqm2
3Block 135 BHK258.0 sqm302.0 sqm2
4Block 145 BHK258.0 sqm305.4 sqm2
5Block 2 Part A15 BHK262.1 sqm309.5 sqm2
6Block 2 Part A25 BHK262.1 sqm307.3 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

20 of 43 compliance document slots are filed as Not Applicable; the remaining 23 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved04-03-2023Water NOC panchayath 04 03 2023.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved18-07-2024NOC KSPCB 2024.pdf
KSPCB- MOEF (Above 50 Acres)Approved04-09-2024NOC KSPCB 2024.pdf
KPTCL- BESCOMApproved06-03-2024BESCOM NOC 2024.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantCA Sagar V2392212000Bengaluru Urban, Karnataka - 560096
EngineerM S Nagendra PrasadBCC/BL-3.6/E-0367/2022-232022Bengaluru Urban, Karnataka - 560011
ArchitectIndrajith Sharad KembhaviCA/2000/266842000Bengaluru Urban, Karnataka - 560001
ContractorSURYA DEVELOPERS-2014Bengaluru Urban, Karnataka - 560064

Builder track record

RERA filing

Surya Developers has 2 other K-RERA-registered projects in our records (average reported construction progress 42%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹2.35 Cr collected from buyers, ₹2.81 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹2.81 Cr) exceeded buyer collections (₹2.35 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress28% → 48% (+20 pts)
Units sold/booked as registered28/44 (64%)
Buyer collections in available QPRs₹25.14 Cr
Escrow withdrawals in available QPRs₹20.76 Cr (0.83x collections)
  • Construction progress moved from 28% to 48% across the filed QPR window.
  • The builder has drawn 0.83x of buyer collections from escrow (about 83% of the ₹25 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹146.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Yelahanka New Town IFSC Code : ICIC0000411 Pin Code : 560064. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport17 km
Outer Ring Road / Manyata19 km
MG Road / city centre26 km
Bellandur–Marathahalli belt33 km
Whitefield IT hub34 km
Electronic City41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Surya Developers.
Surya Developers has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Shree SAI Indira
On track · 50% built · 0% sold
Surya Valencia Phase - II
On track · 35% built · 73% sold

Other RERA-registered projects in Yellupura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.