31 Dec 2017declared completionK-RERA registration · read 20 Sep 2026
80registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.0registered acres

80.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/180328/001650

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2017
Land area4,047 sq m (1.0 acres)
Homes registered80
Tower/wing entries3

In context

Density80 homes per acre
Density in context56th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units80Total inventory registered with K-RERA.
Registered land area4,047 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.75Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)90Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date25-11-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A- BLock43035-
B-Block41520-
C-Block43535-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 80 official flat/unit rows, matching the 80 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK4081.6-98.5 sqm51.3-61.9 sqm25 (15 with 0)
3BHK40105.9-125.6 sqm66.6-79.0 sqm20 (20 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
C-Block3583.5-116.2 sqm52.5-73.1 sqm0 (35 with 0)
A- BLock3081.6-125.6 sqm51.3-79.0 sqm30
B-Block1598.5-118.1 sqm61.9-74.3 sqm15
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A001A- BLock02BHK84.4 sqm53.1 sqm1
A002A- BLock02BHK81.6 sqm51.3 sqm1
A003A- BLock02BHK81.6 sqm51.3 sqm1
A004A- BLock02BHK81.6 sqm51.3 sqm1
A005A- BLock03BHK125.6 sqm79.0 sqm1
A006A- BLock03BHK121.9 sqm76.7 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

4 of 14 compliance document slots are filed as Not Applicable; the remaining 10 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2017 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Phaneendra Mamidala vs ARV InfrastructresRegistration and completion of amenitiesAUTHORITY20/07/2023
G.V. Prabhakar vs S B URBANSCAPESREVOKE (CANCEL) PERMISSION GRANTED BY AUTHORITYAUTHORITY16/06/2026
S RAJA vs ARV INFRASTRUCTURESTo help in registration of the flat . Compensation for untold miseries , hardship , mental trauma and stress.AUTHORITY06/04/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (5 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190624/0003365
24-06-2019
Non delivery of possession, completion of amenities, delay compensation & execution of Sale DeedTemple TreeDISPOSED AO
CMP/190802/0003775
02-08-2019
Non delivery of possession, completion of amenities, delay compensation & execution of Sale DeedTemple TreeDISPOSED AO
CMP/190831/0004043
31-08-2019
Non delivery of possession, completion of amenities, delay compensation & execution of sale deedTemple TreeDISPOSED AO
CMP/200914/0006567
14-09-2020
Registration delay by more than 5 yearsTemple TreeDISPOSED AUTHORITY BENCH6
CMP/201007/0006710
07-10-2020
Flat not registered even after 5(Five)years . Undergoing untold miseries , mental trauma , stress , hardship . Amenities promised not fulfilled and project incomplete.Temple TreeDISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹16.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Marathahalli (IFSC SBIN0040685, a/c …4770). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre3 km
Bellandur–Marathahalli belt10 km
Outer Ring Road / Manyata11 km
Electronic City13 km
Whitefield IT hub17 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Arv Infrastructres.
23 complaints on the K-RERA register against Arv Infrastructres in Bangalore.

Other RERA-registered projects in Shanti Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Temple Tree?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026