Bangalore/Project record

K-RERA · the public record

VNR-GOWRI APARTMENT

· N R CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ4 2025 filing
16units not bookedof 16 · Q4 2025 filing
16registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q4 2025 to Q4 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

2BHK
16

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.1registered acres

145.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1263/419/PR/130226/008466

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area446 sq m (0.1 acres)
Homes registered16
Tower/wing entries1
Unit mix16 × 2BHK

In context

Density145.2 homes per acre
Density in context90th percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units16Total inventory registered with K-RERA.
Official carpet area667 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area890 sqmUseful scale context when comparing density and project cost.
Registered land area446 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.99Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)16Separate filed counts; these categories may overlap and are not added together.
Covered-parking field16Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberGLB-LBPAS-15880/21-22/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date05-06-2025
Project start date01-10-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK16100%667 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
V.N.R GOWRI APPARTMENT4161611.5 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 16 official flat/unit rows, matching the 16 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK1633.2-42.8 sqm21.3-29.4 sqm16

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
V.N.R GOWRI APPARTMENT1633.2-42.8 sqm21.3-29.4 sqm16
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1V.N.R GOWRI APPARTMENT12 BHK41.7 sqm27.1 sqm1
2V.N.R GOWRI APPARTMENT12 BHK42.8 sqm29.4 sqm1
3V.N.R GOWRI APPARTMENT12 BHK42.8 sqm29.4 sqm1
4V.N.R GOWRI APPARTMENT12 BHK33.2 sqm21.3 sqm1
4V.N.R GOWRI APPARTMENT22 BHK41.7 sqm27.1 sqm1
5V.N.R GOWRI APPARTMENT22 BHK42.8 sqm29.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

13 of 31 compliance document slots are filed as Not Applicable; the remaining 18 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

0 of 2 applicable approvals are on file; still outstanding: Engineering Department (PWD) for completion of development works and KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Engineering Department (PWD) for completion of development worksTo Be Applied-View NOC
KPTCL- BESCOMTo Be Applied-View NOC

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantCA AEJAZ AHMED002022Kalaburagi, Karnataka - 585104
EngineerEr. MOHAMMED WAJEED ALIGLB/BL/10480/23-242019Kalaburagi, Karnataka - 585104
ArchitectFirdous KhanamCA/2022/1542522022Kalaburagi, Karnataka - 585104
ContractorNR BUILDERS & CONSTRUCTIONS.-2024Kalaburagi, Karnataka - 585102

Builder track record

RERA filing

Constructions has 19 other K-RERA-registered projects in our records (average reported construction progress 90%). 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered0/16 (0%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹9.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Canara Bank kalaburagi IFSC Code : CNRB0011300 Pin Code : 585101. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~483 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport468 km
Outer Ring Road / Manyata483 km
MG Road / city centre490 km
Whitefield IT hub494 km
Bellandur–Marathahalli belt496 km
Electronic City506 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Constructions.
Constructions has 20 projects registered in Bangalore, 5 completed, 1 past RERA deadline.
2 complaints on the K-RERA register against Constructions in Bangalore.

Other projects by this builder in Bangalore

G.r. Samskruthi
Past deadline · 75% built · 52% sold
K&t's SAI Sannidhi
Filing overdue · 100% built · 68% sold
G V Apartment
On track · 90% built · 0% sold
J V Paradise
On track · 100% built · 100% sold

Other RERA-registered projects in Mathikere

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.