Developer RERA record

IREO

IREO has 5 RERA-registered projects: mixed Gurugram delivery record (2/5 projects with OC); 3 projects past declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
2
Completed / delivered
3
Past declared date
Considering a specific IREO project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (2)click to expand
ProjectCityStatus
THE CORRIDORS (PHASE 1)GurugramOC issued
THE CORRIDORS (PHASE 2)GurugramOC issued
Past declared date (3)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
COMMERCIAL COLONY (MANAGED SERVICED APARTMENTS)Gurugram2020-06
IREO SKYONGurugram2018-11
THE CORRIDORS (PHASE 3)Gurugram2023-12

Figures are Ireo's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.