Developer RERA record

Lewis Infrastructure

Lewis Infrastructure has 8 RERA-registered projects: 1 project under construction, Bengaluru averaging 65% construction; 7 projects past their declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
1
Under construction
7
Past declared date
49%
Bengaluru inventory booked

Under construction

Under construction — 1 project

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
EL ROIBengaluru65%
Considering a specific Lewis Infrastructure project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (7)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
CharisBengaluru2018-06
RAINTREEBengaluru2020-02
24, Defence ColonyBengaluru2019-12
PROVIDENCEBengaluru2021-04
GLORIOUS A2Bengaluru2023-12
NO 3 MILTON STREETBengaluru2024-06
NO 12 LLOYDS ROADBengaluru2024-06

Figures are Lewis Infrastructure's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.