Developer RERA record

Riqueza Estates

Riqueza Estates has 6 RERA-registered projects: 3 projects under construction, Bengaluru averaging 76% construction; 1 project past declared completion date. All figures are the developer's own regulator filings.

Mixed record
Delivery signal
3
Under construction
1
Past declared date
45%
Bengaluru inventory booked

Under construction

Under construction — 3 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Riqueza SiriBengaluru82%
Riqueza SiriBengaluru82%
Riqueza Laughing Earth Phase - IIBengaluru64%
Considering a specific Riqueza Estates project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (1)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
RIQUEZA BARBIEBengaluru2023-02
Registered, no progress filed yet (2)click to expand
ProjectCity
Riqueza Laughing EarthBengaluru
RIQUEZA BARBIEBengaluru

Figures are Riqueza Estates's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.