Developer RERA record

Uppal Chadha Hi-Tech

Uppal Chadha Hi-Tech has 29 RERA-registered projects: 25 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

Flagged
Delivery signal
1
Completed / delivered
25
Past declared date
Considering a specific Uppal Chadha Hi-Tech project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (1)click to expand
ProjectCityStatus
SWAMANORATHNoidaOC issued
Past declared date (25)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
UCHDPL-SECTOR-3-WAVE FLOORSNoida2018-04
SECTOR-5-EWS/LIG-PHASE 02Noida2022-06
UCHDPL-VERIDIA-OAKWOOD ENCLAVENoida2024-09
SECTOR-5-EWS/LIGNoida2018-08
UCHDPL-WAVE GALLERIA-COMNoida2019-09
UCHDPL-SECTOR-4-PLOTSNoida2018-07
UCHDPL-SECTOR-6-PLOTSNoida2019-04
UCHDPL-SECTOR-7-PLOTSNoida2020-11
UCHDPL-SECTOR-15-PLOTSNoida2023-02
UCHDPL-SECTOR-16-PLOTSNoida2023-02
UCHDPL-SECTOR-17-PLOTSNoida2023-01
UCHDPL-SECTOR-18-PLOTSNoida2023-03
UCHDPL-SECTOR-2-WAVE FLOORSNoida2021-04
UCHDPL-SECTOR-2-PRIME FLOORSNoida2020-10
UCHDPL-SECTOR-4-WAVE FLOORSNoida2019-06
UCHDPL-SECTOR-5-WAVE FLOORSNoida2021-04
UCHDPL-DREAM HOMES-GHNoida2021-02
UCHDPL-VERIDIA-3-OAKWOOD ENCLAVENoida2025-10
UCHDPL-WAVE EXECUTIVE FLOORS-GHNoida2021-06
UCHDPL-VERIDIA-4-OAKWOOD ENCLAVENoida2025-12
UCHDPL-VERIDIA-5-OAKWOOD ENCLAVENoida2025-12
UCHDPL-SECTOR-2-PLOTSNoida2018-12
UCHDPL-VERIDIA-6-OAKWOOD ENCLAVENoida2025-12
UCHDPL-VERIDIA-7-OAKWOOD ENCLAVENoida2025-12
UCHDPL-SECTOR-1-OAK WOOD ENCLAVE- PLOTSNoida2021-06
Registered, no progress filed yet (3)click to expand
ProjectCity
UCHDPL- EDENNoida
UCHDPL-SAMRIDDHI HOMES EWS LIG GROUP HOUSINGNoida
UCHDPL-ELIGONoida

Figures are Uppal Chadha Hi-Tech's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.