Gurgaon/Project record

HRERA · the public record

Hightown

REVENUE ESTATE OF VILLAGE SUK HRALI, SECTOR 28 · Silverglades Infrastructure

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units sold that quarterQ2 2026 filing
10 Oct 2026registration expiryHRERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

registration expiry

10 Oct 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

HRERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 18 filed quarterly reports, Hightown records ₹234.19 Cr paid into and ₹236.34 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹8.32 Cr.

₹234.19 Cr

into the escrow account

₹236.34 Cr

withdrawn

₹8.32 Cr

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Official Unit Inventory

306 apartments filed across 7 carpet-area configurations, 10 towers, carpet areas from 194 to 2,497 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).

Carpet area(metric)Units of this size
2,497 sq ft232.0 sq m4
1,991 sq ft185.0 sq m104
1,539 sq ft143.0 sq m2
1,442 sq ft134.0 sq m46
1,238 sq ft115.0 sq m6
1,195 sq ft111.0 sq m98
194 sq ft18.0 sq m46

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2022 Q141260
2022 Q210260
2022 Q38260
2022 Q40260
2023 Q10260
2023 Q23260
2023 Q322260
2023 Q40260
2024 Q12260
2024 Q20
2024 Q30
2024 Q40
2025 Q10
2025 Q20
2025 Q30
2025 Q40
2026 Q11500
2026 Q20

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2022 Q1₹26.82 Cr₹26.80 Cr₹3 L
2022 Q2₹24.67 Cr₹23.74 Cr₹95 L
2022 Q3₹12.79 Cr₹13.09 Cr₹65 L
2022 Q4₹2.24 Cr₹2.89 Cr₹0 L
2023 Q1₹1.75 Cr₹0 L₹3.90 Cr
2023 Q2₹3.78 Cr₹7.58 Cr₹10 L
2023 Q3₹10.16 Cr₹10.13 Cr₹14 L
2023 Q4₹15.32 Cr₹15.46 Cr₹0 L
2024 Q1₹11.98 Cr₹11.35 Cr₹1 L
2024 Q2₹9.98 Cr₹10.61 Cr₹0 L
2024 Q3₹6.89 Cr₹6.78 Cr₹10 L
2024 Q4₹23.20 Cr₹21.24 Cr₹2.07 Cr
2025 Q1₹20.91 Cr₹22.98 Cr₹0 L
2025 Q2₹5.42 Cr₹5.42 Cr₹0 L
2025 Q3₹11.32 Cr₹11.32 Cr₹0 L
2025 Q4₹7.97 Cr₹7.97 Cr₹0 L
2026 Q1₹31.10 Cr₹30.66 Cr₹44 L
2026 Q2₹7.88 Cr₹8.32 Cr₹8.32 Cr

Builder Record

Silverglades has 1 other Gurgaon project on the HRERA register; 0 are past the declared completion date with no OC yet, 1 delivered. Read it as a spot-check list for a pattern, not a delay rate.

  • Merchant Plaza — declared 2020-12-20 · OC on record

Location & Connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Cyber City / DLF Cyber Hub4 km
Udyog Vihar4 km
Golf Course Road belt5 km
IGI Airport, Delhi10 km
IMT Manesar18 km
Connaught Place, Delhi23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Silverglades Infrastructure.
Silverglades Infrastructure has 2 projects registered in Gurgaon, 1 completed.

Other projects by this builder in Gurgaon

Merchant Plaza
Completed · 76% sold

Other RERA-registered projects in Sector 16

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.