HRERA · the public record
Ompee Tower
GURUGRAM, HARYANA · Ompee Construction
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
07 Aug 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 9 filed quarterly reports, Ompee Tower records ₹70.51 Cr paid into and ₹68.45 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹2.06 Cr.
₹70.51 Cr
into the escrow account
₹68.45 Cr
withdrawn
₹2.06 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
60 apartments filed across 2 carpet-area configurations, 2 towers, carpet areas from 1,012 to 1,023 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 1,023 sq ft | 95.0 sq m | 24 |
| 1,012 sq ft | 94.0 sq m | 36 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q1 | 43 | 60 |
| 2024 Q2 | 9 | 60 |
| 2024 Q3 | 0 | 60 |
| 2024 Q4 | 6 | 60 |
| 2025 Q1 | 0 | 60 |
| 2025 Q2 | 0 | 60 |
| 2025 Q3 | 0 | 120 |
| 2025 Q4 | 0 | 60 |
| 2026 Q1 | 0 | 60 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q1 | ₹10.38 Cr | ₹10.38 Cr | ₹0 L |
| 2024 Q2 | ₹5.92 Cr | ₹4.43 Cr | ₹1.49 Cr |
| 2024 Q3 | ₹8.65 Cr | ₹8.65 Cr | ₹1.49 Cr |
| 2024 Q4 | ₹5.97 Cr | ₹5.97 Cr | ₹1.49 Cr |
| 2025 Q1 | ₹6.79 Cr | ₹6.79 Cr | ₹1.49 Cr |
| 2025 Q2 | ₹7.94 Cr | ₹4.98 Cr | ₹4.45 Cr |
| 2025 Q3 | ₹13.62 Cr | ₹17.94 Cr | ₹14 L |
| 2025 Q4 | ₹5.33 Cr | ₹5.46 Cr | ₹0 L |
| 2026 Q1 | ₹5.92 Cr | ₹3.85 Cr | ₹2.06 Cr |
Location & Connectivity
The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 1 km |
| Golf Course Road belt | 18 km |
| Cyber City / DLF Cyber Hub | 21 km |
| Udyog Vihar | 21 km |
| IGI Airport, Delhi | 27 km |
| Connaught Place, Delhi | 40 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.