HRERA · the public record
Smartworld Orchard
SECTOR -61, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA. · Suposhaa Realcon
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
31 Oct 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 4 filed quarterly reports, Smartworld Orchard records ₹0 L paid into and ₹0 L withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹0 L
into the escrow account
₹0 L
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2022 Q1 | 0 | 362 |
| 2022 Q2 | 0 | 362 |
| 2022 Q3 | 0 | — |
| 2022 Q4 | 0 | — |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2022 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q2 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q3 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q4 | ₹0 L | ₹0 L | ₹0 L |
Builder Record
Suposhaa Realcon has 4 other Gurgaon projects on the HRERA register; 1 is past the declared completion date with no OC yet, 3 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Smartworld Orchard — declared 2024-12-31
- Smartworld Orchard — declared 2025-12-30 · OC on record
- Smartworld Orchard — declared 2026-10-29 · OC on record
- Smartworld Orchard Street — declared 2026-06-30 · OC on record
Location & Connectivity
The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 1 km |
| Golf Course Road belt | 19 km |
| Cyber City / DLF Cyber Hub | 21 km |
| Udyog Vihar | 22 km |
| IGI Airport, Delhi | 27 km |
| Connaught Place, Delhi | 41 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.