MahaRERA Property Intelligence · Mumbai City

36 BABULNATH

P51900015000 · BABULNATH · promoter Vinod Mohanlal Jain

Certificate SignedDue 30 Sep 2021

Delivery & Registration

MahaRERA registrationP51900015000
Registered on22 Jan 2018
Promoter-declared completion30 Sep 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vinod Mohanlal Jain is the promoter of record on 22 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
36 BABULNATH1G+2031 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court26152017Disposed
Supreme Court50877/20232023Disposed
Bombay High CourtWPL/34873/20232023Disposed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 5 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202131 Dec 2022Due to delay in receiving NOC to OC from BMC Estates Dept as they are the lessors of the subject property and BMC Estates Dept has formulated a new policy for OTP Calculation and i
30 Sep 202130 Mar 2023The Redevelopment Scheme is on Lease Hold land wherein Lessor is MCGM and they charge One time Premium on surplus area. As the policy for charging OTP is Pending for decision from
30 Sep 202131 Mar 2022Due to the second wave of Covid 19 Lockdown and unavailiblity of Labour force, material and time limit of working hours has caused delayed in our project completion date which is b
30 Sep 202131 Mar 2024The Redevelopment Scheme is on Lease Hold land wherein Lessor is MCGM and they charge One time Premium on surplus area. As the new policy for charging OTP was formulated post decid
30 Sep 202130 Sep 2023Due to delay in receiving NOC to OC from BMC Estates Dept as they are the lessors of the subject property and BMC Estates Dept has formulated a new policy for OTP Calculation in F

Location, Land & Connectivity

Located at BABULNATH, 2ND DADYSETH LANE, Ward ABCD, Mumbai City, 400007. Per the filed land record, the plot is bounded to the north by 40 FEET ROAD, to the south by PLOT NO 35, to the east by 30 FEET ROAD and to the west by 15 FEET SERVICE PASSAGE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)14 km
Chhatrapati Shivaji Int'l Airport16 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Tardeo

Sugan Heights
possession by Aug 2026 · Gulabdevi Jain & Others
Shreepati Skies
Deregistered by MahaRERA · possession by Dec 2026 · Shreepati Skies
Kalikund Heights
possession by Dec 2026 · Kalikund Developers
Mustafa Palace
possession by Dec 2026 · Elite Realty
Servai Tower
possession by Dec 2026 · Inclineestate Developers LLP
Dharam Castle
possession by Mar 2027 · Bhurji Developers LLP

Major developers building in Tardeo

Lodha · 1 project here
Under construction: Marq

Other RERA-registered projects in Mumbai City

379 Vista
possession by Jan 2029 · Ajwaa Developers
41 Grandstand
possession by Jun 2029 · Ramesh Builders
42 East Park
declared completion Apr 2026 · Madhupuri Homes
47 Race Course
possession by Dec 2027 · Akshay Sthapatya Pvt. Ltd.
52 Avenue
declared completion Dec 2024 · Heks Realty
6 Crystal
declared completion Dec 2025 · Crystalstar Housing Developers Private L

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026