MahaRERA Property Intelligence · Raigarh

5P ARIA

P52000013706 · promoter 5P Developers

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP52000013706
Registered on23 Oct 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
5P ARIA1G+531 Dec 2018

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000036475830/03/2023ABHIJEET GOPAL CHORMALE vs Naynesh Niranjan Pandyapending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Dec 2019Due to labor and material supply issue the project is delayed. Kindly issue us the extension

Location, Land & Connectivity

Located at Karjat, Raigarh, 410101. Per the filed land record, the plot is bounded to the north by Plot 12, to the south by Plot 9, to the east by Plot and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~45 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park45 km
Bandra Kurla Complex (BKC)48 km
Chhatrapati Shivaji Int'l Airport49 km
Andheri MIDC / SEEPZ49 km
Lower Parel / Worli business district52 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

SAI Krupa Valley- Phase 1
possession by Aug 2026 · SAI Krupa Developers
Noble Apartment
possession by Aug 2026 · Asra Reality
Madina Complex
possession by Aug 2026 · Al-Hamd Developers
Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Aliza Apartments
possession by Dec 2026 · M/S SKY Homes

Major developers building in Neral

Other RERA-registered projects in Raigarh

7 Kolgaon-Phase-1
possession by Dec 2027 · Satellite Developers PVT LTD
7 OAK Apaprtment
possession by Dec 2026 · Takhatsinh Pravinsinh Rana
79 Lakeview
possession by Jul 2029 · Hari Krishna Buildcon
9 Meraki
possession by Dec 2028 · Ekdant Emperia LLP
99 Silver Oaks
possession by Dec 2033 · Bombay Construction & Infraprojects
A 1 Rishikesh
declared completion Dec 2024 · Dhriti Builders & Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026