AADHUNIK AURA

P51800030800 · BORIVALI WEST · promoter Aadhunik Developers

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP51800030800
Registered on13 Sep 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aadhunik Developers is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
AADHUNIK AURA1G+1031 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BORIVALI WEST, KASTUR PARK, SHIMPOLI, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by SUB PLOT NO 5 AND NEW FINAL PLOT NO 275, to the south by D P ROAD, to the east by SUB PLOT NO 17 NEW FINAL PLOT NO 275 and to the west by SUB PLOT NO 15 NEW FINAL PLOT NO 275. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aadhunik Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Aadhunik Developers

Aadhunik Developers
FlaggedMumbai Suburban
Aadhunik Developers
FlaggedMumbai Suburban
Aadhunik Developers
FlaggedMumbai Suburban
Aadhunik Developers
FlaggedMumbai Suburban
Aadhunik Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Borivali West

Rishabraj Aradhana
possession by Jul 2026 · H Rishabraj Realty
SBI Ragvihar CHS
possession by Jul 2026 · Tuvin Consultancy LLP
Avyukta Neelkamal
possession by Sep 2026 · Shivoham Associates
Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Aadhunik Greens
declared completion Dec 2022 · Aadhunik Developers
Aadhya
possession by Dec 2029 · Gagangiri Construction
Aaditya Plaza
possession by Dec 2026 · JET Build Developers
Aafcon Avenue Girivilla Chsl
declared completion Dec 2023 · Aafcon Developers Private Limited
Aafcon Developers Ashokanand Chsl
declared completion Dec 2021 · Aafcon Developers
Aafcon Harmony
possession by Dec 2029 · Aafcon Builders LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026