06 Apr 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

06 Apr 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000020461

Delivery and registration

When is the project declared for completion?

AARYAHI RESIDENCY is registered with MahaRERA as P52000020461 and the promoter has declared completion for 06 Apr 2025.

06 Apr 2025

declared completion

17months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000020461
Registered on15 Apr 2019
Promoter-declared completion06 Apr 2025
Current statusCertificate Signed
Against todayabout 17 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AARYAHI RESIDENCY record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AARYAHI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
WING A1G+5-
WING B1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vijay Nagar, Nande, Gondhalpada Road, Alibag, Raigarh, 402201. Per the filed land record, the plot is bounded to the north by Survey No 255, to the south by Survey No 253, to the east by Survey No 261 Hissa No 1A and to the west by Survey No 263. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~37 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort29 km
Lower Parel / Worli business district37 km
Bandra Kurla Complex (BKC)44 km
Chhatrapati Shivaji Int'l Airport47 km
Powai / Hiranandani business park50 km
Andheri MIDC / SEEPZ51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Alibag

Excellensea Villas Project
possession by Dec 2026 · Unicorp Realty Private Limited
Balibaug Rekreasi
possession by Dec 2026 · Pushpam Infra LLP
Lakshminarayan CO-OP Housing Society LTD Proposed
possession by Dec 2026 · Elnube Realtors PVT LTD
Swastik Orchid
possession by Dec 2026 · Swastik Developers
Savitri Heritage
possession by Mar 2027 · Mukesh Bhoormal Jain
Shree Radha Krishna Residency
possession by May 2027 · Shree Radha Enterprises

Major developers building in Alibag

Other RERA-registered projects in Raigarh

Aashirwad Heights
declared completion Feb 2023 · Swaraj Developers
Aashirwad Homes
declared completion Dec 2021 · OM SAI Builders AND Developers
Aashray Nisarg
possession by Jun 2028 · Aashray Homes
Aayushi Empire
possession by Sep 2027 · Aayushi Construction
Abhavya Pride
declared completion May 2024 · Abhavya Reality
Abhimaan Altura
declared completion Apr 2026 · Abhimaan Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.