MahaRERA Property Intelligence · Palghar

Aditi Empire

P99000010761 · Vasai West · promoter Rakhumai Developers

Certificate SignedDue 10 Apr 2022

Delivery & Registration

MahaRERA registrationP99000010761
Registered on31 Aug 2017
Promoter-declared completion10 Apr 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rakhumai Developers is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A Wing1G+510 Apr 2021
B Wing1G+510 Apr 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Vasai West, Vasai West, Vasai, Palghar, 401201. Per the filed land record, the plot is bounded to the north by S No 7 and 8, to the south by S No 3 and 1, to the east by 30 mts wide DP Road S No 5 and to the west by Umelman Talao S No 94A and 94B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ28 km
Powai / Hiranandani business park31 km
Chhatrapati Shivaji Int'l Airport32 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district42 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rakhumai Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Rakhumai Developers

Rakhumai Developers
FlaggedPalghar
Rakhumai Developers
FlaggedPalghar
Rakhumai Developers
FlaggedPalghar

Other RERA-registered projects in Vasai

Shree Mahalaxmi Traders
possession by Jul 2026 · Shree Mahalaxmi Traders
Carnival Residency 2
possession by Dec 2026 · Maryland Infra
Emerald
possession by Dec 2026 · Angel-Northwest Homes LLP
Ocean Pearl
possession by Dec 2026 · Gargi Developers
SR Kunj
possession by Dec 2026 · SR Builder
Tahera Residency
possession by Dec 2026 · Gad Realty

Major developers building in Vasai

Other RERA-registered projects in Palghar

Aditi Empire - C Wing
declared completion Apr 2022 · Rakhumai Developers
Aditya Residency
possession by Dec 2027 · Rajesh Sankatha Prasad Shukla
Aditya Residency
possession by May 2029 · Special Developers
Aditya Residency
possession by May 2029 · Ambineon Developers LLP
Aditya Residency
possession by Dec 2029 · Aditi Developers
Adore-4
declared completion Mar 2024 · Ananta Contruction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026