30 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000021184

Delivery and registration

When is the project declared for completion?

Advance Kingdom is registered with MahaRERA as P52000021184 and the promoter has declared completion for 30 Mar 2024.

30 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000021184
Registered on14 Jun 2019
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Advance Kingdom record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Suspended / abeyance — the registration is suspended or in abeyance.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Advance Home Makers is the promoter of record on 5 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Advance Kingdom in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Tiara1G+731 Mar 2023
Pinnacle1G+631 Mar 2023
Pavillion1G+731 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Neral, Dhamote, Kalyan, Thane, 410101. Per the filed land record, the plot is bounded to the north by Survey no 56, to the south by Survey no 53 4, to the east by 18M wide road and to the west by Survey no 53 2A and 2B. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

Advika Hill City-1
declared completion Aug 2026 · M/s Aradhya Developers
Adwait
possession by Dec 2026 · Venkatesh Developers
Aero View Residency
possession by Oct 2029 · Venkatesha Realty LLP
Aeroestate
possession by Dec 2028 · Hoabl Landmark Realty Private Limited
Afsha Apartment
declared completion Mar 2022 · Asad Abdulrehman Fasahate
Agrawals Finopolis
declared completion Sep 2024 · Nupur Highland LLP

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026