Mumbai/Project record

MahaRERA · the public record

AL-QUBA TOWER

Mumbai Suburban · NIDA UNIVERSAL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800004560

Delivery and registration

When is the project declared for completion?

AL-QUBA TOWER is registered with MahaRERA as P51800004560 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800004560
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AL-QUBA TOWER record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nida Universal is the promoter of record on 85 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

85projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AL-QUBA TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
AL-QUBA TOWER1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020NOC from Naval Authority is awaited. Department of Defense, Government of India is reviewing the policy as learnt.
30 Dec 202031 Dec 2023Work is as standstill since December 2016 due to NOC required from Naval Department. Work will be started after receiving the NOC. In view of this you are requested to grant extens

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400070. Per the filed land record, the plot is bounded to the north by CTS NO - 148, to the south by EXISTING ROAD, to the east by EXISTING ROAD and to the west by CTS NO - 572. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)3 km
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district11 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kurla West

Yojan One
possession by Sep 2026 · Meru Realty LLP
Imperial Heights
possession by Nov 2026 · Sumukha Realtors
Buddha Vihar CHS LTD
possession by Dec 2026 · M/S Regal Builders AND Developers
Khaliliya Complex
possession by Dec 2026 · Dani Builders AND Developers
Mantri Business Plaza
possession by Dec 2026 · Mantri Brothers
Rehmaniya Apartments
possession by Dec 2026 · S & S Enterprises

Major developers building in Kurla West

Other RERA-registered projects in Mumbai Suburban

Alag Ananta
declared completion Jun 2026 · Alag Square LLP
Alag Aranya
declared completion Dec 2024 · Alag Aarchie LLP
Alag Artis
declared completion Dec 2024 · Alag Lifespace LLP
Alag Ashtapad
declared completion Dec 2024 · Contour Developers LLP
Alag Capital
possession by Dec 2026 · Alag Property Constructions Pvt. Ltd.
Alag Endeavour
declared completion Jun 2026 · Alag Property Constructions Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026