AMAR GALAXY PHASE - I

Ganesh Nagar · AMAR REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700019634

Delivery and registration

When is the project declared for completion?

AMAR GALAXY PHASE - I is registered with MahaRERA as P51700019634 and the promoter has declared completion for 30 Nov 2024.

30 Nov 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700019634
Registered on14 Feb 2019
Promoter-declared completion30 Nov 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AMAR GALAXY PHASE - I record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AMAR GALAXY PHASE - I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+104.

BuildingWingsFloorsDeclared completion
Building No 11G+104-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Feb 2024Respected Sir/ Madam, We are seeking extension due to time taken for receiving the Completion Certificate (Occupation Certificate) for the said project for which application was
29 Feb 202430 Nov 20241. The only reason we are seeking extension is due to query raised for uploading Completion Certificate (Occupation Certificate) for the said project is uploaded after the revised

Location, Land & Connectivity

Located at Ganesh Nagar, Shivaji Path, Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by S No 123-2 Ramdas Sitaram, to the south by 15M W DP Road, to the east by S No 133 - 5 Mukund Joshi and to the west by 18M W DP Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ26 km
Chhatrapati Shivaji Int'l Airport29 km
Bandra Kurla Complex (BKC)30 km
Lower Parel / Worli business district38 km
Nariman Point / Fort44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Amar Realty is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Amar Realty

Other RERA-registered projects in Dombivli West

Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO
Chintamani Heights & Chintamani Kuber
possession by Dec 2026 · Chintamani Developers
Indira Galaxy
possession by Dec 2026 · Shree Developers
Jai Shree Ganesh Co-Operative Housing Society Limited
possession by Dec 2026 · Shree Vyankatesh Enterprises

Major developers building in Dombivli West

Other RERA-registered projects in Thane

Amar Majestic
possession by Dec 2029 · Amarmaya & Associates
Amar Pushpakunj
declared completion Jul 2026 · Avighna Redevelopers
Amar Vaishali CO-Operative Housing Society LTD
declared completion May 2023 · Joshi Enterprises
Amara
possession by Dec 2026 · Planacres Properties
Amara Business Park
possession by Dec 2028 · Amara Crest LLP
Ambar Kalash
declared completion Apr 2021 · Rudra Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026