Mumbai/Project record

MahaRERA · the public record

Ambika Niwas

Nerul · Sunil Suresh Honrao

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700010934

Delivery and registration

When is the project declared for completion?

Ambika Niwas is registered with MahaRERA as P51700010934 and the promoter has declared completion for 30 Nov 2018.

30 Nov 2018

declared completion

94months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700010934
Registered on31 Aug 2017
Promoter-declared completion30 Nov 2018
Current statusCertificate Signed
Against todayabout 94 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ambika Niwas record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sunil Suresh Honrao is the promoter of record on 175 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

175projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ambika Niwas in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Ambika Niwas1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Nerul, Thane, Thane, 400706. Per the filed land record, the plot is bounded to the north by 576 B, to the south by Plot No 577 B C, to the east by 10 mtr Road and to the west by GES Boundary. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park15 km
Bandra Kurla Complex (BKC)15 km
Chhatrapati Shivaji Int'l Airport16 km
Andheri MIDC / SEEPZ18 km
Lower Parel / Worli business district19 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nerul

Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC
Sawan Serenity
possession by Dec 2026 · Shree Sawan Buildcon

Other RERA-registered projects in Thane

Ambika Palace Phase 1
declared completion Dec 2019 · Dayal Enterprises
Ambika Palace Wing A
declared completion Oct 2021 · Dinesh Narayan Tiwari
Ambrin
declared completion Jan 2023 · Impressions
Ambrin 2
possession by Dec 2027 · Impressions
Ambrin 3
possession by Sep 2026 · Impressions
Ambrin 4
possession by Dec 2030 · Impressions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026