MahaRERA Property Intelligence · Thane

ANAND SAGAR DUOS

P51700016284 · DON BOCCO SCHOOL WADEGHAR · promoter Vpa Developers

Certificate SignedDue 28 Feb 2023

Delivery & Registration

MahaRERA registrationP51700016284
Registered on02 May 2018
Promoter-declared completion28 Feb 2023
Current statusCertificate Signed
Against todayabout 41 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
ANAND SAGAR DUOS BUILDING NO II1G+1528 Feb 2022
ANAND SAGAR DUOS BUILDING NO I1G+1528 Feb 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Senior Divison Kalyan600020/20112011Argument

Location, Land & Connectivity

Located at DON BOCCO SCHOOL WADEGHAR , RAUNAK CITY ROAD , Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by S NO 66 AND 69 WADEGHAR, to the south by 15 MTR ROAD WADEGHAR, to the east by S NO 70 H NO 1-1 Wadeghar Plot-B-2 Bey 18 M ROAD and to the west by S NO 68 WADEGHAR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ30 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

VPA Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by VPA Developers

Other RERA-registered projects in Kalyan

Tharwani Solitaire Phase IV
possession by Jul 2026 · Anil Hardasmal Tharwani
Kailash Gardens
possession by Jul 2026 · Shree Laxmi Enterprises
Mangeshi Ambar
possession by Jul 2026 · Mangesh Dashrath Gaikar
Mangeshi Tulip
possession by Jul 2026 · Mangesh Dashrath Gaikar
Anand 21 Uptown
possession by Aug 2026 · VPA Developers
Pawan Atharva Phase I
possession by Aug 2026 · Pawan Real Estate

Major developers building in Kalyan

Other RERA-registered projects in Thane

Anand Sagar Enclave
declared completion May 2018 · VPA Developers
Anand Upvan NX
possession by Dec 2029 · Ameya Developers
Anand Vaibhav Chsl
possession by Nov 2028 · Sbps Realty LLP
Anandam-A
declared completion Jun 2024 · Pahal Construction Co.
Anandam-B
declared completion Jun 2024 · Geeta Developers
Anandi Height
declared completion Jun 2024 · Prathmesh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026