MahaRERA Property Intelligence · Palghar

ANAND VIEW

P99000003252 · promoter Shree Adeshwar Builder

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP99000003252
Registered on05 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Adeshwar Builder is the promoter of record on 16 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
ANAND VIEW WING B1G+931 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201931 Dec 2019PROCESS FOR OBTAINING O.C OCCUPANCY CERTIFICATE IS UNDER PROCESS.

Location, Land & Connectivity

Located at Thane, Thane, 401203. Per the filed land record, the plot is bounded to the north by 19254818, to the south by 19254722, to the east by 19254783 and to the west by 19254753. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ33 km
Powai / Hiranandani business park35 km
Chhatrapati Shivaji Int'l Airport37 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Rameshwar
possession by Jul 2026 · Chheda Associate
Shalibhadra Yash
possession by Jul 2026 · Sumatinath Builders
Unique Avenue 210
possession by Aug 2026 · Mangalmurti Land Developers
Shree Ganesh Krupa Residency
possession by Sep 2026 · Nutan Construction CO
Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Aleen Heights
possession by Nov 2026 · AB Builders AND Developers

Other RERA-registered projects in Palghar

Anand View A Wing
declared completion Dec 2019 · Shree Arihant Developers
Anand Vihar
possession by Dec 2026 · Aman Realtors
Anand Villa II
possession by Dec 2027 · Mehr Lalit Nihilani
Anandi Nagar
possession by Dec 2027 · Rajesh Manteshwar Joshi
Anandi Palace
declared completion Mar 2022 · Rancy Builders & Developers
Anant Aakash
declared completion Oct 2020 · Pravinkumar Lalchand Jain

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026