Mumbai/Project record

MahaRERA · the public record

Anant Nagar

Palghar · Anant Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 May 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 May 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000005595

Delivery and registration

When is the project declared for completion?

Anant Nagar is registered with MahaRERA as P99000005595 and the promoter has declared completion for 15 May 2023.

15 May 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000005595
Registered on11 Aug 2017
Promoter-declared completion15 May 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Anant Nagar record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Anant Developers is the promoter of record on 124 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

124projects

registered with MahaRERA

14flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Anant Nagar in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Row House no 21G+2-
Row House no11G+2-
Row House No 31G+2-
Row House no 41G+2-
Row House no 51G+2-
Row House no 61G+2-
Row House no 71G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vasai, Palghar, 401201. Per the filed land record, the plot is bounded to the north by H no 2-3, to the south by H no 5, to the east by existing 4-5 M wide road and to the west by Existing 3 M wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ28 km
Powai / Hiranandani business park31 km
Chhatrapati Shivaji Int'l Airport32 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district42 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anant Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Vasai

Carnival Residency 2
possession by Dec 2026 · Maryland Infra
Ariana
possession by Mar 2027 · Mansarovar Estate Builders LLP
Classic Solitaire
possession by Mar 2027 · Sethi Construction CO.
Neminath Pride
possession by Mar 2027 · Shri Neminath Developers
Suruchi Heights
possession by Apr 2027 · Raut AND Associates
Shivneri
possession by Jun 2027 · SAI Builders AND Developers

Major developers building in Vasai

Other RERA-registered projects in Palghar

Anant Sharveshwri Residency
declared completion Dec 2024 · Satish Randhir Singh
Anant Shree
possession by Dec 2031 · Brickwork Infrabuild LLP
Anant Smruti Building NO 02
declared completion Dec 2025 · G.p. Developers
Anant Tower E AND F
possession by Dec 2026 · Shantinath Enterprises
Anant Vjay CO-Operative Housing Society LTD
declared completion Jul 2026 · Imran Pyaralibhai Lakhani
Ananta Apartment
declared completion Mar 2024 · Ananta Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026