MahaRERA Property Intelligence · Raigarh

Ananta Sky

P52000030952 · Near Karjat Railway Station · promoter Gh Group

Certificate SignedDue 30 Nov 2023

Delivery & Registration

MahaRERA registrationP52000030952
Registered on29 Sep 2021
Promoter-declared completion30 Nov 2023
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Ananta Sky1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Near Karjat Railway Station, Station Road, Haveli, Pune, 410201. Per the filed land record, the plot is bounded to the north by SURVEY NO 20A3, to the south by ROAD, to the east by SURVEY NO 23 and to the west by PLOT NO 5. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~50 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park50 km
Bandra Kurla Complex (BKC)51 km
Chhatrapati Shivaji Int'l Airport53 km
Nariman Point / Fort53 km
Lower Parel / Worli business district53 km
Andheri MIDC / SEEPZ54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Anantlaxmi Residency
declared completion Mar 2022 · RAM Infrastructure
Ananya Crystal
declared completion Dec 2022 · Usha Ritesh Verma
Anchit Complex
declared completion Jun 2023 · Prashant Arun Pingle
Anika Apartment
declared completion Sep 2020 · Midas Construction
Anil Residency
declared completion Dec 2022 · R Y Construction
Aniruddha Astha
declared completion Dec 2017 · Yogi Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026