Mumbai/Project record

MahaRERA · the public record

Anmol Sankalp

Plot no 7 · Meenaskhi Madhavanand Bhatt

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000006398

Delivery and registration

When is the project declared for completion?

Anmol Sankalp is registered with MahaRERA as P52000006398 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000006398
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Anmol Sankalp record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Anmol Sankalp in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Anmol Sankalp1G+1531 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Theft at our under construction situated at Plot No. 59, Sector -05, Ulwe,Navi Mumbai, Cables had been stolen by way of cutting the same from the electric meter room and junction b

Location, Land & Connectivity

Located at Plot no 7, Sector 8, Panvel, Raigarh, 410210. Per the filed land record, the plot is bounded to the north by Plot No 58, to the south by 15 Mtrs Wide Road , to the east by Plot No 60 and to the west by 11 Mtrs Wide Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Bandra Kurla Complex (BKC)21 km
Chhatrapati Shivaji Int'l Airport22 km
Andheri MIDC / SEEPZ22 km
Lower Parel / Worli business district26 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharghar

Tharwani Palladian
possession by Sep 2026 · Tharwani Realtors
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary
Krishna Aura
possession by Oct 2026 · Qualitas Lifespaces LLP
Ashwini Apartment
possession by Dec 2026 · Kuldeepsingh Amarsingh Bhalothia
Bhagwati Luxuria
possession by Dec 2026 · Bhagwati Signature LLP
Elysian
possession by Dec 2026 · Devam Ventures

Major developers building in Kharghar

Other RERA-registered projects in Raigarh

Anmol Sonai Heritage
possession by Dec 2029 · Not Available
Annaprabha Complex
possession by Dec 2026 · Kishor Prabhakar Dandekar
Antal Aspire
possession by Dec 2027 · Antal Builders And Developers LLP
Antariksh
possession by Dec 2029 · Bhikhi Developers & Builders
Antilia - 1
possession by Mar 2029 · Bharatkumar Hiralal Shah
Anupam CO OP HSG SOC LTD
possession by Apr 2029 · Kavya Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026