Mumbai/Project record

MahaRERA · the public record

APEX AURA

DRONAGIRI · APEX BUILDCON

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000019129

Delivery and registration

When is the project declared for completion?

APEX AURA is registered with MahaRERA as P52000019129 and the promoter has declared completion for 30 Mar 2023.

30 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000019129
Registered on04 Jan 2019
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for APEX AURA record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Apex Buildcon is the promoter of record on 43 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

43projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for APEX AURA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
APEX AURA1G+531 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DRONAGIRI, 11 M ROAD, Andheri, Mumbai Suburban, 400702. Per the filed land record, the plot is bounded to the north by PLOT NO 12, to the south by PLOT NO 10, to the east by 11 M WIDE ROAD and to the west by PLOT NO 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort16 km
Lower Parel / Worli business district21 km
Bandra Kurla Complex (BKC)25 km
Chhatrapati Shivaji Int'l Airport27 km
Powai / Hiranandani business park29 km
Andheri MIDC / SEEPZ31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Apex Buildcon is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Apex Buildcon project & its RERA track record →

Other RERA-registered projects in Dronagiri

Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra
Avantika Aura
possession by Dec 2026 · Riddhi Developer
Bombay Chalet
possession by Dec 2026 · Bombay Shiva Plus LLP

Other RERA-registered projects in Raigarh

Apex Avenue
possession by Dec 2026 · Apex Realty
Apex Prime
possession by Dec 2029 · Apex Infra
Apple Crown
possession by Dec 2027 · Apple Buildcon
Apramit
possession by Dec 2026 · Pride Developers
Aqua Bliss
possession by Dec 2030 · Dynamix Vacation Resorts Private Limited
Aqua Shores
possession by Dec 2030 · Dynamix Vacation Resorts Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026