Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800008691
Registered on19 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Realty And Developers is the promoter of record on 44 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
ARIANA RESIDENCY WING-A SALE1G+2530 Jun 2021
ARIANA RESIDENCY WING-B SALE1G+2530 Jun 2021
ARIANA RESIDENCY WING-C SALE1G+2530 Jun 2021

Complaints & Orders

25 complaints are on the MahaRERA record for this project, with orders passed in 25. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000094928/09/2017Kamalkant Bajranglal Poddar vs J V Realty and Developers & Orsorder passed
CC00600000039596904/06/2023poojan mehta vs J V Realty and Developersorder passed
CC00600000039655907/07/2023Ashok Shrimant Hirgond vs JV realtyorder passed
CC00600000039656306/07/2023Deepak Vitthal Rawool vs JV Realty & Developersorder passed
CC00600000039656506/07/2023Rupesh Parab vs JV Realty and Devlopersorder passed
CC00600000039658206/07/2023Prakash Patil vs JV Realtyorder passed
CC00600000039654506/07/2023Hirendra Tivarekar vs JV Realty & Developersorder passed
CC00600000039656405/07/2023Dilip Rambachan Gupta vs JV Realty and Developersorder passed
CC00600000039656206/07/2023Darpan Dattaram Hande vs JV Reality and Developersorder passed
CC00600000039655706/07/2023Amit Bharat Parkar vs JV Realty & Developersorder passed
CC00600000039656107/07/2023Kishor Vasant Palav vs JV Realtyorder passed
CC00600000039659707/07/2023Amit Jotiram Salunkhe vs JV realtyorder passed
CC00600000039656706/07/2023Avinash Savlaram Waghmare vs JV Realty & Developersorder passed
CC00600000039657106/07/2023Shatrughan Krishna Kadam vs JV Realtyorder passed
CC00600000039657206/07/2023Shashikant Suresh Sawant vs JV Realty & Developersorder passed
CC00600000039658507/07/2023Aditya Arvind Pawar vs JV realtyorder passed
CC00600000039658426/07/2023Sandeep Maurya vs JV Realty & Developersorder passed
CC00600000039667412/07/2023AMAR HARIRAM ROHRA vs JV Realty and Developersorder passed
CC00600000039755227/09/2023J.V.REALTY AND DEVELOPERS vs Mr.Girish Manchanda and Miss Alka Gabaorder passed
CC00600000042951103/03/2024Shivapushpa Kathirvel Nadar vs Paradigm Realtyorder passed
CC00600000040849620/12/2023Anisha Frank Rodrigues vs M/s. J.V. Realty and developers.order passed
CC00600000042891920/01/2024varsha aditya pawar vs JV REALITY AND DEVELOPERSorder passed
CC00600000042893122/01/2024SNEHAL TONY LOPES vs M/s. J.V. Realty and developers.order passed
CC00600000042895124/01/2024ABHAY BABAN PAWAR vs M/s. J.V. Realty and developers.order passed
CC1250262229/07/2025Girish Manchanda vs J V REALTY AND DEVELOPERSorder passed

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. 5 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Mumbai High Court21801997Decreed
State Consumer Disputes Redressal Commission Maharashtra MumbaiCC/15/4572015Pending
State Consumer Disputes Redressal Commission Maharashtra MumbaiCC/15/4582015Pending
State Consumer Disputes Redressal Commission Maharashtra MumbaiCC/16/4042016Pending
State Consumer Disputes Redressal Commission Maharashtra MumbaiCC/16/4022016Pending
State Consumer Disputes Redressal Commission Maharashtra MumbaiCC/16/4032016Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2022Apart from impact of pandemic, overall progress of construction of Project was dragged on account of certain adversary and restraining orders passed by Hon’ble Bombay High Court wh

Location, Land & Connectivity

Located at Devipada, Borivali (East), Sant Gora Kumbhar Road, Andheri, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by Sant Gora Kumbhar Road-18 30 metres, to the south by 12 metres wide Layout Road, to the east by CTS No 216 and to the west by 12 metres wide Layout Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district25 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Rushabh Apartment
possession by Jul 2026 · R R Builders
Rashmi Manorath
possession by Aug 2026 · Modi's Navnirman Limited
Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Ariha One08
possession by Dec 2027 · Ariha Spaces LLP
Ariha Signature
declared completion Sep 2025 · Shree Fuleshwari Estates
Ariha Skyes
possession by Mar 2029 · Ariha Globe LLP
Ariha Vincere
possession by Jun 2027 · Velstand Realty LLP
Arihant
declared completion Sep 2022 · Plaha AND Mehta Associates
Arihant Amara Sky
possession by Dec 2028 · Arihant Infrastructure Company

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.