MahaRERA · the public record
Arihant Aspire Phase III
Panvel · ARIHANT ABODE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2031
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000056197
Delivery and registration
When is the project declared for completion?
Arihant Aspire Phase III is registered with MahaRERA as P52000056197 and the promoter has declared completion for 31 Dec 2031.
31 Dec 2031
declared completion
63months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000056197 |
| Registered on | 21 May 2024 |
| Promoter-declared completion | 31 Dec 2031 |
| Current status | Certificate Signed |
| Against today | 63 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Arihant Aspire Phase III record 8 quarterly progress reports since registration.
8quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Arihant Abode Limited is the promoter of record on 142 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
142projects
registered with MahaRERA
14flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Arihant Aspire Phase III, ₹53.24 Cr of a declared ₹136.83 Cr estimated project cost is reported as incurred, about 38.9%, as at the last certified filing with MahaRERA.
38.9%
₹53.24 Cr
of ₹136.83 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Arihant Aspire Phase III, 264 of 319 homes filed with MahaRERA are recorded as sold or booked (178 with registered agreements and 86 booked), about 83%, and 55 remain available.
83%sold
264 of 319 homes
₹184.90 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹104.30 Cr (about 56%) is recorded as collected and ₹80.60 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 264 registered agreements, the effective carpet rate is ₹13,832/sqft, with eight in ten falling between ₹12,090 and ₹15,129 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 19 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 267 homes carry one, and 52 of the 319 are recorded unsold. Since we started watching this ledger, 22 homes have moved out of the unsold list, most recently on 11 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| Catalina-403 | 607 sqft | Rs 79.00 lakh typical, over Rs 68.04 lakh to Rs 90.50 lakh | 40 filed on this stack, floors 3–43 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Arihant Aspire Phase III, every one of the 52 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+43 and 319 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| building 01 wing E- catalina | 1 | G+43 | 319 | - |
Unit mix on the filing: 319 residential.
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for Arihant Aspire Phase III, with orders passed in 1 of them.
1complaint
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12400858 | 23/11/2024 | Shanthi Priya Gali vs ARIHANT ABODE LIMITED | order passed |
Location, Land & Connectivity
Located at Panvel, Palaspe, Thane, Thane, 410221. Per the filed land record, the plot is bounded to the north by survey no 13 76 26, to the south by survey no 5 20 31, to the east by Derawali village and to the west by 15 meter wide road. These are the boundaries as recorded in the filed land record.