MahaRERA Property Intelligence · Raigarh

ARUM

P52000025472 · R.P.Nagar Ramwadi · promoter The United Group

Certificate SignedDue 30 Dec 2024

Delivery & Registration

MahaRERA registrationP52000025472
Registered on03 Jun 2020
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, The United Group is the promoter of record on 52 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Building No 11G+8-
Building No 21G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at R.P.Nagar Ramwadi, Panchayat Samiti Road, Pen, Raigarh, 402107. Per the filed land record, the plot is bounded to the north by Internal Road open space, to the south by S No 216B 216A H No 4, to the east by S No 216A H No 6 and to the west by S No 216A1 A3 Plot no 1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

The United Group Of Builders And Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by The United Group Of Builders And Developers

The United Group Of Builders And Developers
FlaggedRaigarh
The United Group Of Builders And Developers
FlaggedRaigarh
The United Group Of Builders And Developers
FlaggedRaigarh

Other RERA-registered projects in Pen

Swami Chhaya
possession by Aug 2026 · Shree Ballaleshwar Developers
Pendse Park
possession by Nov 2026 · F ND H Constructions
Govardhan Greenfields
possession by Dec 2026 · Khelaan Manoj Unadkat
Balaji Tricity
possession by Dec 2026 · M/s Sathe Schemes
Arham
possession by Dec 2026 · IYS Properties LLP
Chandradarshan Enclave
Not filing quarterly progress reports · possession by Dec 2026 · Sunny Rajendra Jain

Other RERA-registered projects in Raigarh

Arundhati MGD CHS
possession by Dec 2028 · Arundhati MGD Sahakari Grah Nirman Sanst
Arvind Arcade
declared completion Jun 2023 · Mandar Enterprises
Arya Paradise
declared completion Mar 2025 · Bhole Balaji & Company
Aryan Advik Villa
declared completion Dec 2022 · Kiran Gajanan Naik
Aryan Corner
possession by Apr 2027 · G R K Infra Developments
Aryan Park
declared completion Dec 2024 · Ayushkranti Builders & Developers PV

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026