MahaRERA Property Intelligence · Raigarh

Aspire Park

P52000019019 · SAI MANDIR · promoter Aspire Buildcon

Certificate SignedDue 30 May 2022

Delivery & Registration

MahaRERA registrationP52000019019
Registered on28 Dec 2018
Promoter-declared completion30 May 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aspire Buildcon is the promoter of record on 11 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
ASPIRE PARK1G+431 May 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SAI MANDIR, Survey no. 56 , plot no. 20 and 21 , Panvel, Raigarh, 410101. Per the filed land record, the plot is bounded to the north by 9 meter internal road, to the south by plot no 19, to the east by plot no 22 and 23 and to the west by 9 meter inetrnal road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

SAI Krupa Valley- Phase 1
possession by Aug 2026 · SAI Krupa Developers
Noble Apartment
possession by Aug 2026 · Asra Reality
Madina Complex
possession by Aug 2026 · Al-Hamd Developers
Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Aliza Apartments
possession by Dec 2026 · M/S SKY Homes

Major developers building in Neral

Other RERA-registered projects in Raigarh

Aspire Swagat
declared completion Sep 2024 · Aspire Developers
Aster
declared completion Jun 2022 · Walmik Raghunath Khairnar
Aster
possession by Dec 2031 · Persipina Developers Private Limited
Astha Avana
declared completion Jun 2026 · Anand Chandanmalji Soni HUF
Astitwa
possession by Dec 2027 · Butala & Shet Assiocates LLP
Astrova
possession by Jul 2026 · Kalpana Sterling Infra LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026