Mumbai/Project record

MahaRERA · the public record

ATHARV RESIDENCY

Thane · PETHE BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 May 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 May 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700009457

Delivery and registration

When is the project declared for completion?

ATHARV RESIDENCY is registered with MahaRERA as P51700009457 and the promoter has declared completion for 30 May 2022.

30 May 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700009457
Registered on22 Aug 2017
Promoter-declared completion30 May 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ATHARV RESIDENCY record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Pethe Builders is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ATHARV RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BILG NO 3 PHASE 11G+230 May 2022
BIDG NO 4 PHASE 11G+230 May 2022
BLDG NO 5 PHASE II1G+230 May 2022
BLDG NO 2 PHASE III1G+430 May 2022
BLDG NO 1 PHASE III1G+430 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Nov 2021DUE TO COVID CONDITION FINANCIAL CRISES AND BOOKING INSTALMENT NOT RECIVED IN DUE TIME PERIOD

Location, Land & Connectivity

Located at Ambarnath, Thane, 412503. Per the filed land record, the plot is bounded to the north by S NO 104 3 TO THE NORTH, to the south by S NO 104 5 TO THE SOUTH, to the east by S NO 104 3 TO THE EAST and to the west by S NO 104 7 TO THE WEST. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~40 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park40 km
Bandra Kurla Complex (BKC)44 km
Andheri MIDC / SEEPZ44 km
Chhatrapati Shivaji Int'l Airport44 km
Lower Parel / Worli business district49 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Thane

Atharva Heights
possession by Dec 2026 · JAI Shreegurutatvam Engineers AND Develo
Atlanta Avadh
possession by Apr 2028 · Atlanta Globalprojects LLP
Atlanta Crown
possession by Apr 2027 · Atlanta Construction
Atlanta Edenworld Phase II
possession by Dec 2028 · SAI Balaji Developer
Atlanta Edenworld Phase III
possession by Dec 2026 · SAI Balaji Developer
Atlanta Luxuria
possession by Dec 2030 · SRI Balaji Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026