MahaRERA Property Intelligence · Thane
P51700026674 · CHIKANGHAR · promoter Balaji World
| MahaRERA registration | P51700026674 |
| Registered on | 21 Oct 2020 |
| Promoter-declared completion | 31 Dec 2025 |
| Current status | Certificate Signed |
| Against today | about 7 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~130.7% of the estimated project cost incurred as of the last certificate (₹40.52 Cr spent against a ₹31.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 95 homes filed with MahaRERA, 80 are sold/booked (65 with registered agreements + 15 booked) and 15 remain available (~84% sold) — selling steadily. Buyers have committed ₹55.42 Cr in agreement value so far. Of that, ₹50.52 Cr (~91%) is already collected, ₹4.90 Cr receivable — a read on how far along these sales really are. Note: the project registers 137 homes in total, but this sold/unsold inventory filing covers only 95 of them — the other 42 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 80 registered agreements, the effective carpet rate is ₹11,407/sqft (typical range ₹10,270–₹13,983) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | D-Office 1 | 1,240 sqft (115.2 sqm) | ₹77.30 Lakh |
| Floor 1 | D-Office 2 | 658 sqft (61.13 sqm) | ₹41.02 Lakh |
| Floor 19 | D-1902 | 616 sqft (57.22 sqm) | ₹39.52 Lakh |
| Floor 28 | D-2801 | 616 sqft (57.22 sqm) | ₹39.52 Lakh |
| Floor 28 | D-2802 | 616 sqft (57.22 sqm) | ₹39.52 Lakh |
| Floor 33 | D-3301 | 616 sqft (57.22 sqm) | ₹39.52 Lakh |
| Floor 33 | D-3302 | 616 sqft (57.22 sqm) | ₹39.52 Lakh |
| Floor 33 | D-3303 | 645 sqft (59.92 sqm) | ₹41.39 Lakh |
| Floor 4 | D-403 | 605 sqft (56.17 sqm) | ₹33.59 Lakh |
| Floor 4 | D-404 | 605 sqft (56.17 sqm) | ₹33.59 Lakh |
| Floor 5 | D-503 | 605 sqft (56.17 sqm) | ₹33.59 Lakh |
| Floor 6 | D-603 | 605 sqft (56.17 sqm) | ₹35.27 Lakh |
| Floor 6 | D-604 | 605 sqft (56.17 sqm) | ₹35.27 Lakh |
| Floor 7 | D-704 | 605 sqft (56.17 sqm) | ₹35.27 Lakh |
| Floor 8 | D-803 | 605 sqft (56.17 sqm) | ₹35.27 Lakh |
⚠ The inventory filing also declares: 38 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+33 and 137 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| WING -D | 1 | G+33 | 137 | - |
Unit mix on the filing: 126 residential and 11 non-residential (shops/offices).
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12503583 | 08/10/2025 | AVINASH PRALHAD HATKAR vs BALAJI WORLD | order passed |
The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2023 | 31 Dec 2024 | In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r |
| 30 Jun 2023 | 29 Jun 2024 | In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas |
| 30 Jun 2023 | 31 Dec 2025 | The delay in completing the real estate project has primarily been due to unforeseen and significant challenges arising from the COVID-19 pandemic, which disrupted operations and h |
Located at CHIKANGHAR, MANGESHI HALL, Thane, Thane, 421301. Per the filed land record, the plot is bounded to the north by 19145325-73082700, to the south by 19144792-73082825, to the east by 19145174-73082931 and to the west by 1914545125-73082656. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 29 km |
| Andheri MIDC / SEEPZ | 31 km |
| Chhatrapati Shivaji Int'l Airport | 34 km |
| Bandra Kurla Complex (BKC) | 35 km |
| Lower Parel / Worli business district | 43 km |
| Nariman Point / Fort | 49 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in BALAJI EXOTICA BUILDING TYPE D PHASE III?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Balaji World is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026