97units filed as unsoldInventory · 20 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
126registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000079004

Delivery and registration

When is the project declared for completion?

BALAJI HEIGHT is registered with MahaRERA as P52000079004 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000079004
Registered on31 Jan 2025
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALAJI HEIGHT record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ncm International is the promoter of record on 13 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In BALAJI HEIGHT, ₹8.33 Cr of a declared ₹24.50 Cr estimated project cost is reported as incurred, about 34.0%, as at the last certified filing with MahaRERA.

34.0%

₹8.33 Cr

of ₹24.50 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In BALAJI HEIGHT, 3 of 126 homes filed with MahaRERA are recorded as sold or booked, about 2%, and 123 remain available.

2%sold

3 of 126 homes

₹1.77 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹46.00 Lakh (about 26%) is recorded as collected and ₹1.31 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 29 homes carry one, and 97 of the 126 are recorded unsold. Since we started watching this ledger, 26 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
4410 sqftRs 45.00 lakh16 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In BALAJI HEIGHT, 8 of the 97 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 96 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 126 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BALAJI HEIGHT1G+9126-

Unit mix on the filing: 126 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NAVI MUMBAI, SECTOR NO-9E, Panvel, Raigarh, 410218. Per the filed land record, the plot is bounded to the north by PLOT NO - 12, to the south by PLOT NO - 10, to the east by TREE PLANTATION and to the west by 15 MTS WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalamboli

Century Heights
possession by Sep 2026 · Prabhu Virji Patel
Manisha Paradise
possession by Dec 2026 · Pruthvi Builders & Developers
Bhaveshwar Aqua - 2
possession by Dec 2026 · Bhaveshwar Infratech
Century Dreams
possession by Dec 2026 · Mukesh Premji Patel
Ddsr Heights
possession by Dec 2026 · Ddsr Builders And Developers LLP
Millennium Urbania
possession by Dec 2026 · Millennium Group

Other RERA-registered projects in Raigarh

Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Balaji Icon
possession by Mar 2029 · Shree Balaji Developers
Balaji Kashish Park
declared completion Dec 2020 · Shree Builcon Private Limited
Balaji Krupa
declared completion Jun 2026 · Balaji Developers
Balaji Palms Phase -II
declared completion Jun 2025 · Balaji Vishwakarma Associates
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026