MahaRERA Property Intelligence · Raigarh

Bella View

P52000017553 · Neral · promoter Pyramid Infratech

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52000017553
Registered on28 Aug 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pyramid Infratech is the promoter of record on 24 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BELLA VIEW1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Neral, Bopele, Andheri, Mumbai Suburban, 401010. Per the filed land record, the plot is bounded to the north by internal road 6 meter, to the south by survey no 49, to the east by plot no 20 and to the west by hissa no 15. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M/S Pyramid Property Consultants. Pvt.ltd project & its RERA track record →

Other RERA-registered projects in Raigarh

Bellavue
declared completion Dec 2025 · Bhakti Developers
Belleza
declared completion Dec 2023 · Saomya Fortune Infra Ventures
Bellezza Woods
declared completion Jan 2020 · Dotom Build Square
Bellim Residency
possession by Dec 2026 · Mohd Khalid Mohd Iqbal Shaikh
Belmac Infinity
possession by Jun 2029 · Supreme Holdings AND Hospitality Limi
Belmac Riverside-I
declared completion Mar 2021 · Supreme Holdings & Hospitality LI

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026