MahaRERA · the public record
BLOSSOM AVENUE
PALGHAR · DILIPKUMAR AMBALAL JAIN
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2030
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P99000066574
Delivery and registration
When is the project declared for completion?
BLOSSOM AVENUE is registered with MahaRERA as P99000066574 and the promoter has declared completion for 31 Dec 2030.
31 Dec 2030
declared completion
51months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P99000066574 |
| Registered on | 11 Jun 2024 |
| Promoter-declared completion | 31 Dec 2030 |
| Current status | Certificate Signed |
| Against today | 51 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BLOSSOM AVENUE record 5 quarterly progress reports since registration.
5quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Dilipkumar Ambalal Jain is the promoter of record on 7 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
7projects
registered with MahaRERA
1flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In BLOSSOM AVENUE, ₹1.64 Cr of a declared ₹45.31 Cr estimated project cost is reported as incurred, about 3.6%, as at the last certified filing with MahaRERA.
3.6%
₹1.64 Cr
of ₹45.31 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In BLOSSOM AVENUE, 0 of 383 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 383 remain available.
0%sold
0 of 383 homes
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for BLOSSOM AVENUE in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 19 September 2026
What the filings record, home by home
Read from MahaRERA on 19 September 2026
No home in BLOSSOM AVENUE carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 383 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 45,274 a sq ft typical, over Rs 26,902 to Rs 49,967.
A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.
The Reckoner Record lists all 383 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 383 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| BUILDING N0 1 A AND B WING | 1 | G+6 | 76 | 31 Dec 2030 |
| BUILDING NO 2 A AND B WING | 1 | G+6 | 76 | 31 Dec 2030 |
| BUILDING NO 3 A AND B WING | 1 | G+6 | 76 | 31 Dec 2030 |
| BUILDING NO 4 A AND B WING | 1 | G+5 | 76 | 31 Dec 2030 |
| BUILDING NO 5 A AND B WING | 1 | G+5 | 64 | 31 Dec 2030 |
| AMENITY BUILDING | 1 | G+2 | 15 | 31 Dec 2030 |
Unit mix on the filing: 368 residential and 15 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at PALGHAR, MANDE VILLAGE ROAD, Vasai, Palghar, 401102. Per the filed land record, the plot is bounded to the north by GUT NO 241, to the south by GUT NO 259, to the east by GUT NO 242 AND 244 and to the west by GUT NO 251 250 AND 248. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 2 km |
| Chhatrapati Shivaji Int'l Airport | 4 km |
| Andheri MIDC / SEEPZ | 4 km |
| Bandra Kurla Complex (BKC) | 5 km |
| Lower Parel / Worli business district | 14 km |
| Nariman Point / Fort | 21 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.