Mumbai/Project record

MahaRERA · the public record

BOMBAY CASTLE

DRONAGIRI · ARVIND LAXMAN PATEL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000015752

Delivery and registration

When is the project declared for completion?

BOMBAY CASTLE is registered with MahaRERA as P52000015752 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000015752
Registered on22 Mar 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BOMBAY CASTLE record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arvind Laxman Patel is the promoter of record on 49 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

49projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BOMBAY CASTLE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BOMBAY CASTLE1G+831 Dec 2022

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for BOMBAY CASTLE, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000047981603/04/2024Bhagavanappa Bhimappa vs Bombay Developerorder passed
CC00600000048025329/04/2024Pooja Shailesh chavan vs Bombay Developersorder passed

Location, Land & Connectivity

Located at DRONAGIRI, PLOT NO 24, SEC 52, Thane, Thane, 400702. Per the filed land record, the plot is bounded to the north by PLOT NO 21, to the south by 11 MTR WIDE ROAD, to the east by PLOT NO 24A and to the west by PLOT NO 25. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort16 km
Lower Parel / Worli business district20 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport27 km
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dronagiri

Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra
Avantika Aura
possession by Dec 2026 · Riddhi Developer
Bombay Chalet
possession by Dec 2026 · Bombay Shiva Plus LLP

Other RERA-registered projects in Raigarh

Bombay Chalet
possession by Dec 2026 · Bombay Shiva Plus LLP
Brahmand Developers
declared completion Jan 2024 · Pravin Pandurang Uttekar
Brahmaputra
declared completion Jun 2024 · Morajkar Estates LLP
Brajesh Sapphire
declared completion Jun 2025 · Life Good Happiness Homes
Bramha Height
declared completion Dec 2021 · Shree Bramha Enterprises
Bramha Heritage
possession by Dec 2027 · Shree Bramha Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026