MahaRERA Property Intelligence · Mumbai Suburban

BRIZO RESIDENCY

P51800008276 · promoter Fatcat Infrastrcture Private

Certificate SignedDue 31 Dec 2017

Delivery & Registration

MahaRERA registrationP51800008276
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 103 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Fatcat Infrastrcture Private is the promoter of record on 3 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
BRIZO RESIDENCY1G+24-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005723109/12/2018Sheldon Vaz vs FAT CAT INFRASTRUCTURE PRIVATE LTDorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400043. Per the filed land record, the plot is bounded to the north by GHATKOPAR MANKHURD LINK ROAD, to the south by DP ROAD, to the east by EKTA CHS and to the west by SERVICE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district12 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Gowandi

Centrio NX BY MJ Shah
possession by Oct 2026 · Lakadawala Developers Private Limited
Domain
possession by Dec 2026 · M/s Build Square
North Star
possession by Apr 2027 · North Property Developers LLP
North Star-2nd Phase
possession by Sep 2027 · North Property Developers LLP
Aventus Heights - Phase 2
possession by Dec 2027 · Ratnaakar Shelters LLP
Dzire
possession by Jun 2028 · M/S Universal Properties

Other RERA-registered projects in Mumbai Suburban

BT Sujata Chsl
declared completion Jun 2022 · C H Patil AND Sons LLP
Buddha Vihar CHS LTD
possession by Dec 2026 · M/S Regal Builders AND Developers
Buildcon Raksha
possession by Mar 2027 · Anaaya Buildcon Infrastructure LLP
Building No. 1 - Sai Indu Tower
declared completion Jun 2025 · G K Realtors
Building No.1 Wing H Olive
declared completion Dec 2025 · S D Corporation PVT LTD
Building NO 2 Ajmera Shikhar
possession by Jul 2027 · Vishal Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026