Mumbai/Project record

MahaRERA · the public record

COMMERCIAL-1

Mumbai Suburban · S M ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700002132

Delivery and registration

When is the project declared for completion?

COMMERCIAL-1 is registered with MahaRERA as P51700002132 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700002132
Registered on31 Jul 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for COMMERCIAL-1 record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for COMMERCIAL-1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
COMMERCIAL-11G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for COMMERCIAL-1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001208625/11/2017Shyamsunder Jangid, Managing Director, Balaji Cars PVT LTD vs SM Associatesorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The High Court Of Judicature At Bombay1202019Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Kalyan Dombivali Municipal Corporation had abruptly cancelled our development agreement and therefore we have initiated Arbitration Proceedings against them in which there is order
31 Dec 201931 Dec 2021The Hon'ble High Court has given order to maintain status quo in civil suit arbitration appeal (ST) No. 11664 of 2019 between Kalyan Dombivli Municipal Corporation as Appellant and
31 Dec 202130 Jun 2024The Hon’ble High Court has given order to maintain status quo in civil suit arbitration appeal (ST) No.11664 of 2019 between Kalyan Dombivli Municipal Corporation as Appellant and

Location, Land & Connectivity

Located at Mahatma Gandhi Road, Andheri, Mumbai Suburban, 421301. Per the filed land record, the plot is bounded to the north by SURVEY NO 10 OF KALYAN, to the south by JUNCTION OF BHIWANDI MURBAD ROAD , to the east by BHIWANDI MURBAD ROAD and to the west by SURVEY NO 6 7 10 21 OF KALYAN. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~37 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park37 km
Bandra Kurla Complex (BKC)39 km
Chhatrapati Shivaji Int'l Airport40 km
Andheri MIDC / SEEPZ41 km
Lower Parel / Worli business district43 km
Nariman Point / Fort45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

S M Associates is the promoter on 6 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every S M Associates project & its RERA track record →

Other flagged projects by S M Associates

S M Associates
Past its declared completion dateThane
S M Associates
Past its declared completion dateRaigarh

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Commercial-2
declared completion Jun 2024 · S M Associates
Concept Arena
declared completion Dec 2023 · Concept Realty
Concorde Realty Kailash Building NO 11
declared completion Dec 2025 · Concorde Realty
Constrcution Of 2557 EWS Tenements At S.no.157/1,village Gotheghar,tal . Dist.-Thane Pmay Project
possession by Jun 2028 · Maharashtra Housing And Area Development
Constructing EWS And LIG Tenements Under Pmay On S No 86 95 And 133 At Shirdhon Tal Kalyan Distthane
possession by Mar 2027 · Maharashtra Housing AND Area Development
Continental Acropolis
declared completion Dec 2022 · Continental Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026