Mumbai/Project record

MahaRERA · the public record

Crown Dombivli 1

Mangaon · LODHA DEVELOPERS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

349units filed as unsoldInventory · 19 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
695registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700048779

Delivery and registration

When is the project declared for completion?

Crown Dombivli 1 is registered with MahaRERA as P51700048779 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700048779
Registered on17 Jan 2023
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Crown Dombivli 1 record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Crown Dombivli 1, ₹53.00 Cr of a declared ₹273.91 Cr estimated project cost is reported as incurred, about 19.3%, as at the last certified filing with MahaRERA.

19.3%

₹53.00 Cr

of ₹273.91 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Crown Dombivli 1, 336 of 695 homes filed with MahaRERA are recorded as sold or booked (310 with registered agreements and 26 booked), about 48%, and 359 remain available.

48%sold

336 of 695 homes

₹161.09 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹136.86 Cr (about 85%) is recorded as collected and ₹24.24 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 336 registered agreements, the effective carpet rate is ₹10,035/sqft, with eight in ten falling between ₹9,810 and ₹10,813 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 346 homes carry one, and 349 of the 695 are recorded unsold. Since we started watching this ledger, 22 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
F-0006459 sqftRs 45.51 lakh typical, over Rs 43.62 lakh to Rs 54.05 lakh205 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Crown Dombivli 1, 83 of the 349 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 348 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 695 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Coral A1G+1396-
Coral B1G+13112-
Coral C1G+13112-
Coral D1G+1396-
Coral E1G+13141-
Coral F1G+13138-

Unit mix on the filing: 695 residential.

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Crown Dombivli 1, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039724826/08/2023Vinod Harindar Chauhan vs Lodha Crown (Macrotech Developer Limited)order passed
CC00600000042875907/01/2024Karthik Gopal Mudaliar vs lodha crown dombiviliorder passed

Location, Land & Connectivity

Located at Mangaon, Mangoan, Mumbai City, Mumbai City, 421203. Per the filed land record, the plot is bounded to the north by 55 part and 56 part, to the south by 53 by 1 part and 53 by 2 part, to the east by 51 Part and to the west by 65 part And 65 by 9 part. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Hedutane

Ambrin 3
possession by Sep 2026 · Impressions
Liana C
possession by Sep 2026 · Lodha Developers Limited
Casa Belvedere
possession by Oct 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited
Patels Pearl
possession by Oct 2026 · Pramukh Developers
Ashokas Empire
possession by Dec 2026 · Ashokas Empire

Major developers building in Hedutane

Other RERA-registered projects in Thane

Crown Dombivli 2
possession by Dec 2028 · Lodha Developers Limited
Crown Dombivli 3
possession by Aug 2027 · Lodha Developers Limited
Crown Dombivli 4
possession by Jun 2028 · Lodha Developers Limited
Crown Residency
declared completion Mar 2026 · Crown Builders AND Developers
Crown Splendora - Tower 1
declared completion Nov 2025 · Lodha Developers Limited
Crystal Antras
possession by Dec 2028 · Luxora Realtors Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026