MahaRERA Property Intelligence · Palghar

DARSH APARTMENT

P99000024576 · NEAR PIONEER SCHOOL · promoter Sadguru Builders Developers

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP99000024576
Registered on24 Feb 2020
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sadguru Builders Developers is the promoter of record on 114 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
BUILDING NO 5 WING A1G+330 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202331 Dec 2026DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME

Location, Land & Connectivity

Located at NEAR PIONEER SCHOOL, PARASNATH, Vasai, Palghar, 401404. Per the filed land record, the plot is bounded to the north by OPEN SPACE, to the south by INTERNAL ROAD, to the east by WING B and to the west by INTERNAL ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sadguru Builders & Developers is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sadguru Builders & Developers

Sadguru Builders & Developers
FlaggedPalghar
Sadguru Builders & Developers
FlaggedRaigarh
Sadguru Builders & Developers
FlaggedRaigarh

Other RERA-registered projects in Palghar

Shree SAI Apartment
possession by Jul 2026 · Shree SAI Jivdani Developers
Madhav Vatika - VI
possession by Jul 2026 · R M N H Developers LLP
Prithvi Anand Kuber Complex
possession by Jul 2026 · Prithvi Anand Housing And Land Developer
Vardhaman Divine
possession by Jul 2026 · Vardhaman AND Shah Associates
Symphony Heights
possession by Aug 2026 · Kreate Space LLP
Shree Puram - 2, Building No. 1
possession by Aug 2026 · Vastu Realities

Major developers building in Palghar

Other RERA-registered projects in Palghar

Darshan Complex
possession by Dec 2027 · Kishor Walhe
Darshan Developers
declared completion Dec 2025 · Darshan Developers
Darshan Lifestyle - Tanishq D Wing And E Wing
declared completion Dec 2023 · Parks Developers LLP
Darshan Swapnalok Phase 1
declared completion Sep 2020 · Intelligent Landmarks LLP
Darshan Swapnalok Phase 2
possession by Jan 2029 · Intelligent Landmarks LLP
Darshan Swapnalok Phase 3
possession by Aug 2031 · Purehomes Lifespaces LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026