Mumbai/Project record

MahaRERA · the public record

DARSSHAN VONALZO

SHANKAR SHETH LANE · JAYANT ENTERPRISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900016780

Delivery and registration

When is the project declared for completion?

DARSSHAN VONALZO is registered with MahaRERA as P51900016780 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900016780
Registered on12 Jun 2018
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DARSSHAN VONALZO record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jayant Enterprise is the promoter of record on 51 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

51projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DARSSHAN VONALZO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
DARSSHAN VONALZO1G+831 Dec 2023
DARSSHAN VONALZO1G+831 Dec 2023

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for DARSSHAN VONALZO, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000037505412/04/2023SETH R A AND M R DUBASH TRUST THRU ADVOCATE MR VIJAY A. RAJPUT TRUST vs JAYANT ENTERPRISEorder passed

Location, Land & Connectivity

Located at SHANKAR SHETH LANE, NAUSHIR BHARUCHA ROAD, , Mumbai City, Mumbai City, 400007. Per the filed land record, the plot is bounded to the north by SHANKAR SHETH LANE, to the south by NAUSHIR BHARUCHA MARG, to the east by CS NO 5 and to the west by CS NO 7 8 9. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ19 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Tardeo

Shreepati Skies
Deregistered by MahaRERA · possession by Dec 2026 · Shreepati Skies
Mustafa Palace
possession by Dec 2026 · Elite Realty
Krypton Crown
possession by Mar 2027 · Krypton Creation
Shree Sammet Shikhar Heights
Not filing quarterly progress reports · possession by Dec 2027 · V M Homes PVT LTD
Araia
possession by Dec 2027 · Kavita Dimension LLP
Fortune Aura
possession by Dec 2027 · K Realtors

Major developers building in Tardeo

Lodha · 1 project here
Under construction: Marq

Other RERA-registered projects in Mumbai City

Darul Faiz
declared completion Jun 2022 · NEW Empire Builder & Developer
Darul Mustafa
possession by Dec 2027 · Citymaker Builders Private Limited
Datta Enclave
declared completion Dec 2024 · Shree Datta Developers
DB Turf View
possession by Dec 2026 · Turf Estate JV
DB Views
possession by Dec 2026 · M/s Shree Shantinagar Venture
Decor Tower
declared completion Jan 2021 · Decor Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026